ee er RS

a ee

CHAPTER #, SECTION 1
its population. Planning and engineering heretofore described had been modified and extended
by the character of the developing test program,
and construction in place had reflected its then
known requirements. Holmes & Narver Management, delega.ing most facilities design to Field
Engineering forces, had devoted its Home
Office Engineering staff to close scientific liaison
and priority design of structures as quickly as
criteria became firm.
The early concept of OPERATION CASTLE as it affected the scientific structures program was that it would consist of two ground
shots with zero stations and related photographic and recording stations of the general
magnitude of the Mike shot in OPERATION
IVY. In addition, the decision was made to trv
a detonation using a barge anchored in the
lagoon for the zero point. This concept was later
expanded to include three ground zero detonations and three barge shots, and in the fall of
1953 another barge shot was added, making a
total test program of seven shots.
Early in OPERATION CASTLE the HEN
Engineering Division reviewed many of the
major structures used in OPERATION IVY
and. based on this review, prepared advance
estimates of materials required for similar
structures anticipated for OPERATION CASTLE. Procurement of standard materials from
these advance estimates made it possible to start
a flow of materials to the Atolls prior to completion of design. This technique often made it
possible for the Field forces to start construction
immediately upon receipt of approved design
drawings.
The newdesign criteria developed at Los
Alamos were transmitted by J-6 Division, and
H&N worked ciosely at UCRL with their Project
Engineers in development of criteria for the
Laboratory’s construction requirements.
Experience gained during OPERATION
IVY with the 9000-foot plywood tunnel containing a controlled atmosphere envelope for

observations taken on the Mike shot led to a

decision to use pipe arrays in OPERATION
CASTLE between the zero point and recording
stations to accomplish the same general purpose.
The information gained from a UCRLbuilt test section of this pipe served as the basis
for the design of pipe arrays used in each
CASTLE ground shot. The pipe technique imposed rather tight alignment and vacuum retention specifications. Pipe was designed and
fabricated early in the program and subsequent
construction and alignmen! problems were
successfully solved.
The proposal to use a barge as a zero point
introduced a problem of maintaining stability
but it was eventually determined that a zero
point of this type would be feasible.
Page 1-6

In order to outtit the 500-ton barges it was
necessary to design a bargeslip at Elmer with o
traveling gantry crane which could be used for

construction of the barge superstructure as well

as fo. final installation of cquipment by the
Users. In addition. it was necessary to design
an assembly area at Elmer where critical components might be stored and eventually assembled and moved onto tie barges. This area incorporated facilities provided in previous operavions by the USS Curtiss.
Organizing the test structures construction
phase of OPERATION CASTLE required a
considerable amount of logistical planning because of the large area over which the construction activities were conuacted. In ord:r to use as
few men as possible on Bikini Atoll ind to avoid
duplication of facilities, it was dev.ded that all
matenals would be shipped through the Elmer
central warehousing and accountir:. facilities,
and that only a limited warehous.ig activity
would be set up at Tare to hand!e constructicn
in that area and to act as a redistibution point
for materials destined to other sites in the Bikim
Lagoon. It was planned that the only exception to this would be those items, such as H-heam
steel piling, structural steel, and equipment,
which were of such size and of such an easily
identifiable nature that logicaliv they should
be discharged at Tare. The assignment of an
LST by TG 7.3 as the primary means of transporting materials and equipment between the
two Atolls made it necessary to carefully evaluate in advance the necds for construction
equipment in order that infrequent trips of a
landing ship dock (floating drydock) might be
used to transport equipment such as cranes
which cannot be carried on an LST without
dismantling.
One of the main construction problems involved in a program of this magnitude and
compressed time tables was that of scheduling
materials to avoid delavs in the program. The
normal procurement and shipping time on mat-

erials, and particularly on fabricated equipment

and structures, was three to four months. Realizing that this had to be shortened for those
Stations which were designed late in the program, tt was necessarv to take unusual action
in all phases of the supply process. For example,
in order to expedite fabrication for Zero Stations
designed late in the program, it was necessary
to obtain a line drawing from Engineering prior
to actual design, and from this drawing the
Procurement Department canvassed suppliers
to determine where material was available, and
time-and-material-type contracts were awarded
upon these forecasts. This succeeded in

placing a hold on the material and allocating
time in vendors’ plants. As designs were firmed

up, the vendors were allowed to proceed with
fabrication, and by expediting movement of ,

j
f

Select target paragraph3