CHAPTER |, SECTION 1

On site Fred, Eniwetok Island, the amount
of actual additional facilities required was net
agreed upon until rather late in the program, and

during the summer and fall of 1953 this phase

of the work assumed larger proportions. An important element affecting the work load was
the decis:on to move the base of alr operations
from Kwajalein, where it had been in previous
tests, to site Fred at Eniwetok. Because of this
decision, It was necessary to expand the facilities; to improve the airstrip paving from the
standpoint of both impact load and area; to
furnish additional parking area. a decontamination pad, additional warehouse buildings; and
to augment the electrical distribution system
to that area. Task Group 7.2 required addittonal recreational facilities. administrative buildings. and general improvement in manyof the
camp areas. In addition, it became necessary
to increase the water supply.
Also affecting the Eniwetok work load was
“Typhoon Hester” which occurred on 29 Decambar
1952, and “Tynhooen
Doris” which
ia
= 7
—
Br
t
occurred in December 1953: these storms made

necessary the rehabilitation of many structures
and areas, and pointed up the necd for additional shore protection from storms, particularly
on site Fred. This action was taken. Buildings
im general, appeared adequate for storm wind
pressures.
To engineer the added facilities on both
Elmer and Fred, maximum use was made of
prefabricated buildings for such structures as
the laundry, administration buildings, barracks,
and mess hall. Existing prefabricated buildings
had proven their adaptability to this type of
use and had a fine record for withstanding the
climatic conditions, including the high winds
encountered during typhoons. The new warehouses at both sites were of steel frame with
aluminum siding. This was considered to be
the most economical type of building suitable
for warehouse structures in that climate. To
resolve the problem of beach erosion on the
ocean side of Fred, a seawall of poured concrete

was designed, requiring a minimum cost for
installation, to provide maximum protection
against wave action resulting from storms. This
wall was extended only in the areas which were
observed to be most vulnerable and where existing facilities had suffered the most damage
during “Typhoon Hester.”
The engineering
design of airport facilities was coordinated with
the Air Force in order that their needs for handling manytypes of aircraft dunng the Operation

would be met. Approximately two-thirds of the

airstrip was paved, including the taxiways which
were provided, and improvements to the existing facilities were made, such as vroviding a
concrete floor for the B-50 hangar. A newconcrete pad was designed to provide an area for
washing down contaminated planes.

Construction of the additional facilities on
Elmer, at Eniwetok, was accomplished in the
summer andfall of 1953 as time could be spared
from the scientific program. Const-uction work

proceeded without unusual incident. Site Fred

construction was coordinated with the priorities
established by the Using Agencies, and in many
cases construction schedules were made contingent upon help supplied by TG 7.2 in the erection of buildings and other work requiring unskilled labor. Many prefabricated structures that
had formerly been at Kwajalein were re-erected,
using a large percentage of TG 7.2 labor. The
paving of theairstrip and related iterms of work
Were correlated with air operations and were
accomplished with a minimum of interruption
to air traffic.
Construction work in this period progressed
without abnormal incident, though the rather
heavy work load. resulting from an accumulation of work orders, especially those involving
preliminary clectrical work requests, placed a
burden on the scheduled construction at a time
when the scientific program was at its peak,
with the result that many items of work were
not accomplished as promptly as would have
been the case under normal conditions. The installation of a submarine power cable between
the two sites solved a power problem and made
it possible to supply site Fred with approximately 1000 KW from the Elmer power plant.
The Fred power plant was then used as a
souree of standby power and. primarily, for
furnishing power to the distillation plant during
peak loads.
The site plans for all camps are shown in
F gures 1-3 through 1-9 at the end of this
Cc .apter.

The scientific structures program, intimately identified with the primary mission of the
proving ground development and always crucial
t> the logistics and completion schedule of the
( ontractor, had been gradually emerging concarrently with the design and construction of
lise facilities to support the test operation and
Page 1-5
Lyte

activity. The base facilities considered to be
permanent for the Pacific Proving Ground are
located on sites Elmer and Fred at Eniwetok
Atoll. In order to provide accommodations for
the anticipated population, including a new peak
high of 3,000 men on Fred, it was determined
that certain changes would have to be made to
existing facilities. On Elmer these changes consisted of: additions to the laundry and mess
hall. an engineering wing on the administration
building, a personnel wing for the administration
building, new barracks, an additional 1000 KW
generator in the power house, additional distillation equipment, and a general revision to the
power supply and distribution systems of both
sites, including a submarine power cable between Elmer and Fred.

Select target paragraph3