CHAPTER If, SECTION 5 CONSTRUCTION. Work was scheduled to start on 15 September and to be completed on 31 December. Actual construction started on 10 December and was completed on 2 January 1954. STATIONS 145.01 - 145.07 INSTRUMENT CANS SITE ENIWETOK LAGOON USERS: ONR and NOL GENERAL.EachStation consisted of a five-ton instrument can placed in the Eniwetok Lagoon as designated vy the User. ENGIMEERING. The spotted the locations, Survey Department CONSTRUCTION. The Marine Department placed the moorings furnished by the User and assisted the User in securing the cans to the moorings. Work was started on 7 April 1954 and was completed on 14 April. STATION 145.27 - 145.29 INSTRUMENT CANS SITE BIKINI LAGOON JSERS: ONR and NOL GENERAL. These Stations were located off site George in the Bikini Lapaon and were similar to the 145 series. These Stations were autheized on 6 June 1954 and were used in connection with the Station 30 detonation. STATIONS 162.01 AND 162.02 SHORE RECORDER SITES NAN ind TARE - USER: ONR GENERAL. The Stations consisted of recorder units furnished by the User. ENGINEERING. One drawing was submitted on 18 August and was approved 3 November. CONSTRUCTION. The work involved consisted of furnishing wiring and assistance in the intallation. Work was undertaken in December STATIONS 170.01 - 170.05 ACCELEROMETER STATIONS SITES - VARIOUS - USER: SANDIA GENERAL. These five Stations were located as follows: 170.01 on site Tare, 170.02 and .03 on site Sugar and 170.04 and .05 on site Pearl. The work involved ccnsisted of placing User equipment from 15 to 30 feet m the ground and encasing this equipment in concrete. This equipment measured ground accelerations. Completion dates varied from 10 December to 10 April. STATIONS 210.01 - 210.61 FILM BADGE STATIONS (ON STAKES) SITES VARIOUS - USER: ESL GENERAL. Stations 210.01 thru 210.41 and 210.53 thru 210.56 were located on the various islands and reefs of the Bikini Atoll. Stations 210.42 thru 210.52 and 210.57 thru 210.61 were located on the various islands and reefs of the Eniwetok Atoll. These Stations were Film Badge Stations to measure the gamma total dose, and each Station consisted of a two-inch aluminum rod embedded four feet into the land or reef. The land Stations projected two feet above grade: the reef Stations projected four feet above the high water line. ENGINEERING. Criteria were received on 12 May 1953, drawings were started on 7 July and submitted for approval on 9 July. AEC approved same on 25 July and prints were issued on 31 July. Originally only Stations 219.01 thru 210.52 were authorized. On 28 October, Stations 210.53 thru 210.59 were added and on t March 1954, Stations 210.60 and 210.61 were likewise added. Figure 2-95 is tynical for the series and shows Station 210.23 on Oboe as completed on 5 January 1954. CONSTRUCTION. Work was scheduled to commence on 1 November and to be completed on 31 January 1954. The starting dates of the individual Stations on Bikini varied from 11 November to 31 December. The completion dates varied from 5 January to 29 January. On Eniwetok. the starting dates varied from 31 December to 19 January 1954 and Stations were completed on 25 January with the exception of Stations 210.60 and 210.61. These two latter Stations were started on 1 March 1954 and were completed on 6 March. STATIONS 22001. 9°0 08 - 990.14 DOUBLE DETECTOR STATIONS SITES VARIOUS - USER: ESL GENERAL. These Stations were located on various islands in the Bikini Atoll. The work involved consisted of embedding User’s equipment in approximately three cubic yards of reinforced concrete. The cquipment measured gamma dose versus time. ENGINEERING. The original design criteria were received on 29 May and a revised list of Station numbers and locations was received on 2 July. One drawing was started on 7 July, ENGINEERING. Theoriginal design critera were received on 11 May 1953. Drawings 1» quired were included with Station 220 series. submitted on 9 July and approved on 28 July. Ore detail drawing was submitted on 29 November and approved on 22 December. CONSTRUCTION. Work was scheduled to commence on 1 October and to be completed on 15 January 1954. Actual construction starting dates varied from 7 September to 2 Decemb: r. commence on 1 November and to be completed by 15 January. Actual starting dates varied from 9 November to. 18 January; completion Page 2-102 CONSTRUCTION. Work was scheduled to