CHAPTER II, SECTION 5 123.06 and 123.07 were deleted. On 9 Septeriber Station 12°..01 was relocated and Stations 123.04 and 123.05 were deleted. Drawings were started 16 June and were included with the Station 122 series. CONSTRUCTION. Work was scheduled to commence on 1 November and to be completed by 10 February 1954. Actual construction started 11 November and was completed on 26 December. STATIONS 130.01 - 130.07 - PITOT GAGES SITES VARIOUS - USER: SANDIA GENERAL. These Pitot Tube Gage Mount Stations were identical to the Station 315 series; description is reported under the 315. series. These gages were to be used to record shock winds and after winds. ENGINEERING. Criteria for Stations 130.01 thru 130.05 were received on 11 May. Or 9 July, Station 130.06 was added and on 9 September pm hos footing to which were attached gages for cahbrating lorce, drag, temperature and density. Figure 2-94 shows this Station as 90S completed on 5 December. The Station vas located on the shore line and required protection from possible tidal and wave damage. Extra concrete was poured in front of the Station as noted in the photograph. ENGINEERING. The original design critema were received on 9 September. One drawing “is required which was started on 10 September, and included with the Station 130 series. CONSTRUCTION. Work was scheduled to commence on 15 September and to be completed on 30 January 1954. Actual construction started on 19 November and was completed on 23 January 1954. STATION 142.02 - TEST HOLE PIT SITE FOX - USER: ONR GENERAL.This Station was a test hole, or pit, and ‘vas used for determining underwater pressure versus time. ENGINEERING. This Station was relucated from George to Fox, as an clevation of pius ten feet was required. Test hole No. & was available and used. CONSTRUCTION. Work was started on 20 December 1953 and was completed 23 January 1954. STATIONS 143.01 - 143.44 BUOY WITH ANCHOR SITE BIKINI LAGOON - USER: ONR Figure 2-94. Stations 130.07 and 131 90% Completed Station 130.07 was Likewise added. Figure 2-94 includes Station 130.07 on site George and it is shown 90°% completed on 5 December. Design data is reported under the 315 series. CONSTRUCTION. Work was scheduled to com- mence on 1 October and to be completed on 10 January 1954. Actual construction starting time varied from 7 September to 15 December. Completion dates vaned from 9 January to 25 January 1954. STATION 131 MULTIPLE PITOT TUBE MOUNT SITE GEORGE - USER: SANDIA GLNERAL. conerete buoy jecting above were attached water pressure These Stations were reinforced anchors with a hooped har proand below the anchor to which instruments for measunng underversus time. ENGINEERING. The original design criteria were received on 29 June 1953. One drawing Was required which was started on 24 July, submitted on 5 August and approved and released on 2 Septembez. CONSTRUCTION. Work was scheduled to commence on 15 September with completion on 31 December. Actual construction started 10 December and all Stations were complevwd and placed by 2 January 1954. STATION 144.01 - 144.16 BUOY ANCHORS SITE BIKINI LAGOON - USER: GNR GENERAL. This Station consisted of a con- GENERAL. These Station. were reinforced concrete buoy anchors and were used to record underwater pressure versus timo, pipe had a three-inch round conduit embedded ENGINEERING. The criteria were received on 23 July. Drawings required were ‘ncluded with the Station 143 series. crete footing 5° x 20’ x 5’ deep with four 8” I. D. pipes embedded in the footing and projecting three feet above the top of the footing. Each in the concrete and extending to the side of the Page 2-101