CHAPTER It, SECTION 5
CONSTRUCTION. Originally, construction was
scheduled to commence cn | November 1953 and
to be completed by 31 December. Due to the
low priority assigned to this construction, the
completion date was advanced to 10 February
1954. The construction starting dates of the
individual Stations varied from 11 November to
2e January. The completion dates varied from
21 January to & February.
STATIONS 250.01 - 250.59
MOORING WITH FLOAT
SITES VARIOUS - USER: NRDL
- Figure 2-95.

Stations 210.23 and 220.08
Typical

GENERAL, Each Station of this series consisted of a 45-gallon drum float, painted yellow,
secured in piace by a concrete cube anchor with
cable and used to measure fallout distribution.

SITES VARIOUS - USER: ESL

ENGINEERING. The original criteria were
received on 30 April 1953 fur Stations 250.01
thru 250.26. On 23 July the criteria was amended toe inereane the number of Stations to 59.
On 10 September one Station was deleted; the

GENERAL. ‘These Stations were located on
sites William, Yoke, Zebra, Alfa and Bravo.
The work involved consisted of embedding User
equipment which measured gamma dose versus
time in the ground. No concrete was required.

Stations 240.01 thru 250.26 were located in the
Bikini Lagoon and Stations 250.27 thru 250.238
were assigned to the Emwetok Lagoon. One
drawing was started on 12 June, completed on
24 June and approved on 14 July,

dates varied from 2 Januaryto 23 January 1954.
STATIONS 221.01 - 221.05

ENGINEERING. The original design criteria
were received on 9 July and are reported in the
Station 220 series.
CONSTRUCTION.
Work was scheduled to
commence on 1 December and to be completed
on 31 Janary 1954. Actual construction started
on 31 December. Completion dates varied from
5 January 1954 to 23 January.

STATIONS 231.01 - 231.15
WIDE FLANGE MOUNT
SITES VARIOUS - USER: NRL
GENERAL. For land Stations, a 20-foot pile
wes used with @ five-foot nroiection. On reefs, 2
25-foot pile was used with a ten-foot projection.
These Stations were for neutron flux and

spectrum measurements.

ENGINEERING. Theoriginal criteria for Stations 231.01 thru 231.08 were received on 1
May 1953. The User desired a wide flange
beam capable of withstanding 25 psi pressures.
This required a steel H-pile embedded for 15
feet in depth. On 29 July 1953, newcriteria
required the addition of an aluminum rod which
projected four feet above each pile. On 2 September 1553, criteria changes increased the number of Stations thru 231.15. On °2 October 1953,
all Stations, except 231.02 thru 231.05 and
231.13 thru 231.15, were cancelled. On 2 January 1954, Stations 231.13 thru 231.15 were
relocated to a different site. One drawing was

started on 7 July 1953, submitted on 9 July,

and approved by AEC on 28 July; the drawing

was issued on 31 July.

remaining

Stations were

renumbered

so that

CONSTRUCTION. The work was originally
scheduled to start on 15 September and to be
completed by 31 December. Due to its low work
priority, the completion date was extended to
25 February 1954. Construction for Stations in
the Bikini Lagoon was started on 9 September
and completed on 16 January. For the Eniwetok
Lagoon, the Stations were started on 8 September and were completed on 23 January. All
work was completed in January, but by 25
February, 12 tloats at Eniwetok and seven floats
at Bikini had broken loose. This was caused by
cable abrasion against the coral. The cable size
was increased from !'4 to !y-inch and moorings were relocated. After the initial test at

Bikini, many of the floats were lost. On 26

March 1954, Stations 250.25, .49, .52, .53 and
.56 were deleted.

STATIONS 251.01 - 251.10
CONCRETE BOX
SITES VARIOUS - USER: NRDL
GENERAL. These land instrument Stations
were located on various islands in the Bikini
Atoll to measure fallout distribution.
Each
Station consisted of a reinforced concrete box
8-4" x 8-4” x 5-0" high. There was no top or
bottom to the box, which was embedded four
feet into the ground; the lower two feet of the
box was filled with coral sand. Figure 2-96
shows Station 251.02 completed on Fox; this
example is typical of the series.
ENGINEERING. The original design criteria
were received on 30 April 1953. Minorrevisions
Page 2-103

4 ae tee,

ave sed

_

Select target paragraph3