CHAPTER II, SECTION 2
activities occurred. Through somesacrifices by
User personnel in shortening oeneficial occupancy time and partially eliminating their pre-test
dry runs, all stations were readied in time. This
may be noted from Figure 2-3, which indicates
that by 1 May 1955 much ofthe lag in progress
had been overcome and that the schedule for
scientific Test facilities was essentially met.
The construction progress of permanent

base projects is shown in charts at end of this
discussion. Due to the urgency that developed
in construction of expendable test facilities,

it became necessary to concentrate men and

equipment on this work and to defer the con-

struction of less vital permanent base projects.
Therefore, the actual progress attained on overall permanent base construction was not in

phase with predicted progress. However, when
men and equipment could be spared from work
on scientific facilities, the work on deferred projects was undertaken again.

away from the main bases throughout the construction period as the supporting vessels made
only one call at each site. The over-all problem
was overcome by carefully planning equipment
usage for the construction phase of each structure with the idea of utilizing all equipment.
This involved a considerable movement of equipment between sites in order to meet require-

ments. It also necessitated rigid scheduling of
the various crafts in order that placement of
reinforcing steel, and electrical, mechanical, and

other related items would fit the plan for equipment usage.

Extensive construction activities were re-

quired on the reefs at both Eniwetok and Bikini Atolls. Tidal conditions and weather were
important factors. To overcome the difficulties

inherent to working in sea water of varying

depths, various measures were employed. Concrete was precast where practicable. In some
cases forms were prefabricated, then set at low
tide, and concrete was poured using tremies.

Equipment had to be serviced frequently and

even with the most thorough preventive main-

tenance, salt water action seriously impaired
its life. To reduce shutdowns because of breakdowns, mixers of two transit-mix trucks were

removed from their chassis and installed on
trailers. Wagon drills and compressors used in
aggregate production and a crane used for pile
driving were similarly mounted. This not only
reduced breakdowns but permitted work to proceed on the reefs for longer periods.

tay

During

December 1955, the Proving Ground was subject to heavy seas, which periodically occur in
this area. This caused considerable damage to
construction in place on the reefs, the deadlining of some heavy equipment, and the loss
of a number of small tools. These conditions
occurred during a period of intense activity. By

concentrating men and equipment on the affected projects, the temporary setback in progress
caused by these high seas was overcome without ©
a serious effect on the over-all program.

Figure 2-17.

Placing Planking for Bulkhead

One of the most difficult problems experienced was that of scheduling the use of con-

struction equipment, since sufficient

equipment

was not always available to adequately outfit
the construction crews at each site. This was

especially true of concrete-placing and welding
equipment, trucks, cranes andtrailers. Of parti-

cular significance in this respect was the requirement for such equipment at off-atoll construction sites. This equipment had to remain
Page 2-18

Exploration was made early in the program
to determine suitable sources of coral aggregate;
possible reef locations were selected from
samples tested by the Field Engineering Force.
As the aggregate was generally obtained from
these reef locations, the rate of production was
necessarily slow due to normal difficulties encountered in subaqueous excavations. The use
of wagon drills and compressors mounted on
trailers permitted operations to proceed at higher tide levels than normally possible had standard wheel-mounted wagon drills been used. To

ensure maximum production with minimum op-

erational interference, all blasting was performed
after the regular working day. Stockpiling of
the aggregate was both logical and economical.

The testing laboratory made two gradation
checks on each day’s operation to ensure that

aggregate was within specified gradation limits.

Select target paragraph3