WETAK ATOLL

Runit (Yvonne) Cleanup and Crater Containment

20 The suggestion

Commander, JTG. MG Tate reviewed the JTG plan for the selective
excision of the Runit hot spots. Recognizing that the available dome space

toposed by Field
ected again on the

of approximately 6,000 cubic yards would not accommodate all the

spreading of low-

contaminated soil from Fig-Quince, the JTG had developed a sequential
plan for excising one-sixteenth hectare areas having transuranic readings
over 160 pCi/g, working from hottest to coolest areas (highest to lowest
readings). The initial excision would be limited to 2,000 cubic yards to
minimize the possibility that all of the contaminated soil stockpiled at
Lujor and Aomon might not be encapsulated. Dome capacity permitting,
subsequentlifts would be made based on DOE re-IMPing on a one-quarter
hectare grid and newareas of highest readings determined. This procedure
would be continued until all one-quarter hectare areas had been reduced to
less than 160 pCi/g or dome capacity no longer existed. Once encapsulation
of all soil ceased and capping operations became thecritical path, the
USAEwould place a 12-inch blanketof relatively clean soil (less than 160

lhe Commander,
maximum effort
Lujor soil and to
and Aomon. No
. To carry out this
sctive excision of
)Runit.121

mand anticipated
‘ould be possible,
ndicate increased
sked to develop a
the focus on the
twas to be given
l effort on Lujor;
mplete the soil
he plan on crater

pCi/g) over the Fig-Quince area.!25 This plan for selective excision of

contaminated soil in the Fig-Quince area appeared to offer the best
opportunity to make a substantial change in the radiological condition of

Runit within the available crater dome volume, considering the potential
loss of volume to other possible excision requirements on Boken and
Lujor growing out of the DOE Fission Products Survey (subsurface). On |
June 1979, the Commander, Field Command approved the JTG plan,

iat excavation of
: Structure would
‘nt and proposed
soil wasinitially

emphasizing that completion of the soil removal and the containment
operation was essential to the accomplishmentof the cap completion by 15

September 1979 and subsequent demobilization on schedule. !26

uidance directed

/ low transuranic
nsport to Runit
rackfill initiated.
‘n soil transport
remaining to be
dor, and 4,900
een transported
od soil yet to be
‘ximately 5,600
operation was
sited Enewetak

umand. Colonel

ichspies as the

Here ¢ in Hane to

ch time as the

oil.123 Actually,

451

Once all Boken, Enjebi, Aomon, and Lujor soil had been encapsulated,
and the Fission Products Data Base Survey had shownno furthersoil to be
excised, the Runit excision plan was put into effect. Survey results before
and after the selective lifts are shown in Figures 8-36 through 8-42. The
final result, after removal of 5,015 cubic yards of soil, was a 75 percent
reduction in surface contamination in the Fig-Quince area.!27 Although
this was probably the most highly contaminated soil excised on theatoll,

no air sampler readings exceeded the action level of 10 percent of the

maximum permissible concentration (MPC), with the highest reaching
0.04 MPC. On 26 July 1979, soil cleanup operations were terminated on

Runit, and final capping of the dome commenced. A final radiological
characterization of the Fig-Quince area was made by DOE-ERSP, and a 12-

inch blanket of clean soil was placed over the excised area. As a final
check, a complete surface characterization of Runit, using the IMP, was
made by DOE-ERSP in December 1979.

d
a
a

iW

H

H
Hi

fy
i

|

i

Select target paragraph3