CHAPTER II, SECTION 5
=

venues!
" .

Figure 2-163.

as
.

ee £

Station 2300 - 55°. Completed

pleted by 15 February 1954. Actual work started

on 25 August and was completed on 20 January.
Figure 2-163 shows an estimated completion of
55% as of 15 October. The reinforcing steel in
the foreground represents only a part of the
stec] requircd to bo worked inte the woner side
walls and roof slab. Figure 2-164 shows the east
- or rear wall of the Station as completed. The
platform and light at the left of the Station was
Station 1812.07. Difficulty was experienced in
pouring the heavily reinforced limonite concrete
key monolithic with the coral concrete foundation of this Station. On the similar pour for
Station 2300, this was remedied by providing
reverse forms for the limonite pour, which was
made after the surrounding coral cement had
set.

STATION 2310 - MIRROR SHED
SITE TARE - USER: UCRL
GENERAL. Station 2310 was a 12’-0” x ..8’-0”
x 8 - 0” high wood building resting on a series
of steel trestles ten feet high. The structure had
a wocd floor, plywood and stud walls, and ply-

wood andjoist roof. The floor of the Station had
two exposed steel I-beams for the purpuse of
mounting optical instruments. The dest.n re-

quired that a 1000-pound load applied anywhere

Figure 2-164.

Station 2300 - Completed

. be 3, JO

along the I-beams, or a 20-mph wind would
not cause a slope of the 1-beams of more than

two minutes of arc. For this reason a riveted

trestle-type support, braced continuously in
both directions, was used inthe design of the
Station. Electric power was supplied from Station 50. The Station was used for Project 23.1
(high speed photography).

Page 2-146

eee
at ap lh

:

7 me
-

- 4a

,

rE

cat Ne whe whe! cecelicea,

Select target paragraph3