CHAPTER II, SECTION 5

Figure 2-106.

Station 1202 - 89% Completed
i

for alignment purposes. Two insulating pipe
sections, 20 feet long, were provided for each

pipe;

however.

7 ¥

On 19 December 1952, an alignment procedure was submitted to UCRL which covered the

during early tests, failure

alignment of a continuous pipeline 10,000 feet

which were furnished by the User, are deserihed

conducted at the juusite were receiverl snow-

occurred in an insulating section and they were
eliminated. Provisions were made in each of the
12 pipes for connecting vacuum pumps for
evacuating the pipeline. The vacuum pumps.
under Station 1204.03.

in length, to a horizontal and vertical tolerance
of plus or minus 0.5 inch from a line of sight
between working points at the extremities of
the line. On 23 January 1953, results of tests

;
ENGINEERING. The original design critena
for this Station were received from UCRL in a
letter dated 18 December 1952. At that time
it was planned to construct a seven-pipe array
approximately 9,500 feet long on the TareSugar-Roger group of islands at Bikini. The
location was later changed to site Charlie. and
the number of pipes was increased to 12. In the

ing solar radiation did not adversely affect
alignment of a section of 8 5 8” O.D. pipe.
Investigations were conducted in comperation
with UCRL representatives to obtain suitable
expansion and insulating joints. A 1,000-foot
trial section of pipeline was constructed at
UCRL, Livermore, California, and tested. In
the meantime, the specification for the pipe
was received from UCRL who had made preliminary arrangements to secure it for the various arrays from Armco Drainage and Metal

ical, would have to be held in a straight line
from the device to the detector. It was further
established that the pipeline should be designed
to withstand a wind of 35-mph without movement and a wind of 90-mph with movement,

Manager for further processing through Armco
Drainage and Metal Products, [nc., and delivery to Jobsite. Preliminary design work undertaken is noted above. Working drawings were
started on 8 May and seven drawings and

origina! criteria it was established that the alignment of the pipeline, both horizontal and vert-

although after a 90-mph wind it would be ex-

pected that minor adjustments, repair and re-

alignment would be required.

Products, Inc. The procurement of this materia] was turned over to H&N bythe Field

seven sketches were submitted from 14 May
to 1 December. Approvals were dated from 3

June to 8 January 1954.

Page 2-112

OPCe tne emer tt

ne ee

Fe a

Select target paragraph3