CHAPTER If, SECTION 5

e+ Aad . llrect bcd. SoAssidae mead ,
i

ed

a‘?

ai ll aS

a be Joe
ae

-

a!

ie

-

f

fs
ad
Figure 2-98.

Station 1200 - 25% Completed

by tie rods. These Stations were for Rad Chem
analysis, Project 11.1.
ENGINEERING. Thecriteria were received on
1 October. Two drawings were started on 27
October. The drawing for Station 1110 was
submitted by 3 November and approved on 21
December. The drawing for the other Stations
was submitted on 27 October and approved on
17 November.

CONSTRUCTION.

Work was scheduled to

commence on 1 November and to be comp!cted
by 31 December. Actual construction starting
dates varied from 6 to 20 January. All Stations
were completed on 30 January 1954.

STATION 1120.01
PORTABLE COLLECTOR - SITE ZEBRA
USER: LASL

¢

corridor and utility room that housed the electrical and mechanical equipment. Access to the
utility room was provided through a 4’ - 2”
wide x 9’ 0” high tunnel. At about 18 feet from

the end of the utility room. the tunnel turned

90 and extended for about 40 feet on a slight
upward grade to a covered entrance. The tunnel
entrance had two openings, each enclosed by
a steel, blast-resistant door. A 5’-0” x 7’-0" protected area outside the opening was completely
housed hy a smail reinforced concrete box-like
structure called the vestibule. The main entrance opened onto a reinforced 16’-0” x 20-0”
concrete ioading platform and a 20’-0” x 68’-0”
loading ramp. This Station was used for Reaction History, Project 12.1.

STATION 1200 - RECORDING STATION
SITE CHARLIE - USER: UCRL

MECHANICAL.
Dehumidification was provided in the three instrument rooms. The
corridor utility room was ventilated with filtered fresh air. The rooms were kept under a dry
air pressure preventing infiltration of large
quantities of humid corridor air whenever the
doors to these rooms were opened. Conditioning
units in each room recirculated, cooled and reheated the room air as required to maintain
desired conditions.

GENERAL. This was a heavy reinforced, earth
covered rectangular structure, 41'-0” x 49’-0”
with a tunnel entrance. It was divided into
three rooms and opened at one end into a

ELECTRICAL. The power to the Station was
received from the gencrators at Station CH-500
through three 75 KVA transformers’ in Substation CH-1200-X. One feeder served the light-

GENERAL. An area with a 25-foot radius was
staked out and cleared in the center of which
a geographic position was determined.
This
Station was for a sample cullection, Project 11.2.

ue!
woot

Page 2-107
.

:

oe.

1

i

3

boynem

ulebes wii atas re ocd

}\

Select target paragraph3