JOHNSTON ATOLL
:
SCIENTIFIC
F &S NO.
TITLE
01053
Scientific Laboratory - Subtasks C501, C502, C503, C504, C507,
C515, C516, C701, C702, C910 and C920
USER

STRUCTURE /FACILITY NO.

TC

,

SCIENTIFIC STATION NO.

190

BoD

None
FOD

FUNDING
AGENCY

($000)

JTF-8
MILCON

PRE-GO
Prior Cost

CRO7-64
CRO4-65

POST-GO
Est. 2/65

ENGR

PROC

29.0

CONST

53.6

200.5

TOTAL

FURN

283.1

,
|

TOTAL

12,0

29.0

53.6

200.5

283.1

12.0

COMPLETED

DESCRIPTION

This is an 80 x 140-ft. prefabricated steel frame building with

corrugated asbestos siding, insulation and a concrete floor slab.

The building

provides offices and laboratory space for assembly and testing of DW instruments, data analysis and sample counting operations. The interiorof the building includes partitions, doors, a 9 1/2-ft.

suspended ceiling, toilet facilities

and a darkroom. Itis air conditioned and climate controlled. Substation SS50815 provides 300 kva of 480/277 volt, 3:_phase secondary power. An additional
transformer, in series, provides 75 kva of 120/208 volt power.

was completed in 1966,
DRAWINGS:

The building

91-190-Cl

91-190-El1 thru b4

91-190-Al thru A3

91-190-M1 thru M6

91-190-S1

,

F 91-190-W1l

POS T-GO

PROCUREMENT Furniture will be procured.
CONSTRUCTION Workbenches will be installed and receptacle strips will be
provided over the workbenches.

1-53

VOL I