177

Mobilization

Operation Switch also created increased demands for billeting at

Enewetak Atoll. Building 686 on Enewetak was pressed into service as

overflow billets, and incoming personnel who were scheduled to work in

the north were sent promptly to Lojwa Camp. There were some problems

in retaining necessary skills to assure continuous operational capability

during the exchange—and, as was obvious, the loss of experience,
continuity, and working relationships was staggering. In general, however,

Operation Switch I was very successfully executed.!04

MOBILIZATION/CLEANUP OVERLAP
Although 15 November 1977 was identified, for scheduling and record

purposes, as the end of the Mobilization Phase and the beginning of the
Cleanup Phase, in practice, mobilization and cleanupefforts overlapped by
several months. Some cleanup operations began long before 15 November
1977, and some mobilization efforts were not completed until muchlater.
During the first week of December 1977, seven navigational aids were
installed by personnelof the U.S. Coast Guard Enewetak LORANStation,

with technical guidance by Mr. Steve Guishikumaofthe I4th Coast Guard

District, and with boat support by the USNE. Navigational lights were
installed at the Enewetak personnel pier, on the derelict concrete ship off

Japtan, on the Point Oscar survey platform, on the east end of Biken

(Leroy) Island, and on the landing ramps at Runit, Lojwa, and
Enjebi.195,106 These aids significantly increased the safety of boat

operations at dawn and dusk, and for any emergency boat operations
required during the hours of darkness.
As was previously noted, Lojwa camp construction was seriously behind
schedule, and CJTG was urging that work be accelerated to provide
beneficial occupancy as scheduled by IS November 1977. Through many
well-conceived and well-directed actions, this was achieved, although

somefacilities were incomplete. The powerplant, distillation plant, billets,
and most other major facilities were complete; however, the dining hall
was not used until 25 December 1977, when the first meal served was

Christmas dinner. Burnout latrines and water trailers were used until
planned facilities were finished.!°7 Temporary water lines and other
makeshiftfacilities were gradually replaced, some as late as February 1978,
as camp construction phased into camp maintenance (Figure 3-20).

Through superb teamwork as well as many outstanding individual
efforts, mobilization for the Enewetak Radiological Cleanup Project was a
success. By 15 November 1977, the base camps were ready to support the

cleanup forces. The equipment to locate, remove, and dispose of
contaminated material was on hand, and the forces were deployed and
ready to begin cleanup operations.

Select target paragraph3