QUAN. UNIT TOTAL COST Site - Elmer: Approximately 37 lineal feet of 7'-0" high, wood frame and plywood partitions were added, to make two additional offices, and an existing wood rail was removed; Building 176, Personnel Office. Construction Contract Cost MWO 141: Shelter. mwo 147: Site - Fred: 168.31 168.31 Site - Elmer: A concrete slab, 54'-0" long x 20'-6" wide x 4" thick poured under existing Building 360, DUKW Repair Construction Contract Cost Bach 1,134.27 Each 1,134.27 Repairs to asphalt runways and parking areas were made as follows: (A) Existing runway from Station No. 00-50 to Station No. 30-50 was seal-coated. (B) Le-13, Parking area was repaired by scarifying the (C) The existing runway was patched, broomed and cleaned, area, the loose material then bladed into windrows, flattened, sprayed with diluted Bituminal, mixed, bladed, sprayed evenly and rolled. surfaced with tack coat of diluted Bituminal, and then cold mixture of sand and Bituminal spread and rolled to a compacted thickness of 3/k". XIGNAddV MWO 138: II TTEM NO. A-35 - MISCELLANEOUS MAINTENANCE WORK ORDERS (Continued ) “TOA 26-1 DESCRIPTION OF PROPERTY UNITS