CHAPTER 18.2
ROLL-UP OPERATION
Except for delays caused by safety considerations, except for min-~
or modifications of originally contemplated procedures to comply with
instructions of the AEC Resident Engineer, and except for minor changes

to meet unanticipated post experiment conditions, the published roll-up

procedure has been or is being followed. Table 18.1-1 indicates the
assignment of roll-up activities to departments of H & N and shows sche-

duled and actual completion by dates and percentages.

TABLE 18.2-1, ROLL-UP STATUS AS OF JULY 15, 1951

Progress - %

iten_

Scheduled

Actual

100%

100%

Scheduled

Completion

Remarks

Design Dept.

Damage Survey and
Completion Report

Data

Campleted
July 6

t.

Zero Area Crater

Surveys

September 15

Delayed

by radio-

activity

in zero

area

High Tide Line

Survey

Existing Structures

Survey

67%

50%

August 5

5%

10%

September 15

Tope 1000! Radius

Zero Areas for 1!

Contour

October 1

To start
July 15

November 30

To start

Resurvey High Tide
Lines at 4-Month
Interval

Revise Precise Con-

trol Field Sketches

18-2

37%

50%

September 1

Oct. 15

Select target paragraph3