116

RADIOLOGICAL CLEANUP OF ENEWETAK ATOLL

Planning and Programming

117

MOBILIZATION

*

MAT. /SUPPLIES

CS

PROCURE
SHIP

|

ALEMBEL

J) BILLAE

EQUIP.

;

PROCURE
SHIP

il

|

CONSTRUCTION

BASE: CAMP

'

REMOTESITE

CLEAN UP
TEAM A
TEAM B

"
i

TEAM C

UNIBOR
'

t

>

DEMOBILIZATION

.

|

(
_t

3
Zz

A. BoKO

SY. MUNIOR

\ INEDRAL
JIMEOROL

a

AMANIJ

BIKEN

see+—jae

fone

Southwag!

Paccage

Containment would be accomplished by mixing contaminated soil,
cement, and salt water into a slurry and pumping the mixture through
pipes to a tremie barge, then to the bottom of the crater. By keeping the
discharge end of the tremie pipeat least | foot beneath the top surface of
the previously placed slurry, a monolithic mass would be accumulated,
gradually displacing the water from thecrater. All contaminated debris was
to be removed from theislands and encapsulated in the slurry during this
phase. When the water becametoo shaliow to float the barge, the tremie
operation would stop and the slurry line would be held by a crane moving

slowly around to form a mound. During the inactive periods in the

containment operation, Team C personnel would assist Team B in their
cleanup of Runit, the last and largest soil cleanup operation. After all
contaminated debris and soil had been contained, a cleanup of the
containment site would be conducted to assure that afl contaminated
material was in the container before the concrete cap was begun.. The
container would be covered with an 18-inch-thick concrete cap. Once the

-

with noncontarminated

!

material to provide a structure moreresistantto the effects of the sea. 248

!

taken from the Enewetak Engineering Study and adjusted for such factors

I

1

y RUMIT

————

9

JEDROL

FIGURE 2-7. OPERATION SCHEDULE (MONTHS).

:

Ocean

DREKAFIMON
TEAM G

P
Be
Hog
a5

>

The CONPLAN cleanup schedule was based on man-hour estimates

as weather, radiological safety, and emergencies.24? The concept planners
estimated that cleanup of all plutonium contamination over 40 pCi/g on Il

en"

O2/ JAPTAN
Seep Entrance

* MEBREN

SS

|

g
peic\

arts?”

RISEWO

Ocean

BOKER

yy
BOKANDRETOK

“ EWEWETAK

(BASE CAMP TEAM A)

ew

2

4

NAUTICAL

5

MILES

FIGURE 2-8. ARMY ENGINEER TEAM ASSIGNMENTS.

islands would require removal of 125,000 cubic yards of soil.250 Th

recognized the many uncertainties in their estimates and the
many

unknowns in

the

mission,

especially the radiological cleanu .

Consequently, theyset no fixed dates but provided only a general estimat
e
for project completion. CONPLAN estimates ranged from 2] to 25 months
for cleanup operations, including demobilization of base camps. 251.252

SUPPORT ELEMENTS
The Joint Staff planners attempted to distribute the Enewetak project
tasks among the Services as equally as possible while retaining unit

Select target paragraph3