66

RADIOLOGICAL CLEANUP OF ENEWETAK ATOLL

Planning and Programming

QUARANTINE OF RUNIT: MAY 1972

kind; clearing of vegetation; and construction of roads
in connection with
PACE. From October 1972 until a court hearing in
June 1973, AFWL
prepared a draft Environmental Impact Statement
(DEIS), held public
hearings at Ujelang Atoll in an attempt to obtain dri-En
ewetak support

During the May 1972 AEC survey, several bits of metal with centimeter-

two low-order detonations there. The presence on Runit of discrete pieces
of metal contaminated with plutonium presented a new and serious

concern.!4 The senior AEC representative, Mr. Roger Ray, recommended

woeee

low-order Fig shot and similar to residue found on Johnston Atoll after

eae

range dimensions were found on Runit. Three fragments were hand-

carried to the University of Washington for analysis, where they were
identified as plutonium-contaminated beryllium. They appeared to be
residue from the nonnuclear detonation of the Quince shot or the very-

asked the AEC Nevada Operations Office (AEC-NV) for additional data
on the nature of the hazard which might then allow completion of
PACE.!7 On 30 June 1972, DNA and AECrepresentatives met and agreed
that an additional survey should be made to determine if PACE might
safely resume on Runit. That survey was carried out from 26 July to 2

August 1972 by AEC and DOD personnel. Safe zones wereidentified in
and around the Fig/Quince area. The quarantine waslifted to permit work
in those zones, and PACE operations on Runit continued until September
1972 when the program wasagain halted, this time by a restraining order
issued by the U.S. District Court in Honolulu at the request of Mr.
Mitchell, the dri-Enewetak’s legal counsel. The principal bases of the
complaint were that the PACE Project had been started before DOD had
filed a final environmental impact statement; that DOD had refused to
hold hearings on Ujelang Atoll; and that the decision to conduct PACE on
Enewetak was a violation of both the National Environmental Policy Act
Cer es
4
\DVaA Tas Ot

19

On 5 October 1972, the District Court ruled that the plaintiffs were
entitled to an injunction because of the violation of NEPA and, therefore,
PACE activities, including core drilling and seismic surveys at Enewetak,

were prohibited. The injunction included a prohibition on excavation of
land, reef, or beach areas; core drilling; detonation of explosives of any

went ee ee ee
arn

not remove any vehicles, equipment, or materials until adequate
decontamination procedures could be established. The AEC’s
recommendation was intended primarily to prevent further aggravation,
through dispersion, of an already difficult contamination problem and did
not imply that activities to date had caused any significant personnel

Considering previous results, the quarantine seemed somewhat severe
to DNA. Since the quarantine stopped PACE operations on Runit,. DNA

and reorganized the PACE test plan. The court hearing
resulted in

cancellation of the cratering experiments: however, the
geological portions
of PACE were permitted to continue as the Explor
atory Program on

Eniwetok (EXPOE)whichis described ina subsequent section.
20

Before the restraining order and injunction halted
PACE activities on
the atoll, a 19-acre area covering approximately one-fif
th of Aomon had
been excavated to form a large depression for use
as a bed for a 1000-

pound high explosive parametric test shot. The court ordere
dthat the area
be restoredto its original profile. DNA obtained Mr. Mitchell's
approval of

immediate quarantine of Runit; i.e., to cease all operations thereon and to

exposures.!5 In response to the AEC’s recommendation, the U.S. Air
Force Space and Missile Test Center (SAMTEC), which then managed the
atoll, put the quarantine into effect on 22 May 1972.16

67

a modified stipulation to accomplish the restoration
in conjunction with
the forthcoming radiological cleanup project or,
if the project were
cancelled, as a separate action.2! When the cleanu
p project was approved
and funded, restoration of the PACE test bed was
included in the cleanup
project operation plan.
During preparations for PACE, large quantities of high
explosives were
stockpiled on Medren. These became excess when PACE
was cancelled
and they were transferred to the TTPI for use in channe
l clearance in the
Marshall Istands District. Unfortunately, the ship charte
red bv the TTP] to
remove the explosives was overloaded, foundered, and
sank a few
hundred miles from Enewetak Atoll: however, the crew
was rescued.

ASSIGNMENT OF RESPONSIBILITIES: JULY-NOV
EMBER 1972
On 17 July 1972, the Assistant Secretary of Defens
e for International
Security Affairs, ASD(ISA), advised DNA that DOD
planned to conduct
the cleanup of Enewetak Atoll with the technical
support of AEC. He
requested that DNA initiate planning actions with
AEC to identify the
scope of work and the resources necessary for this
mission.22 During the
next month, DNA presented a series of introductory
briefings on the
project for officials of the Office of the Secretary
of Defense and Joint

Chiefs of Staff GCS) and met with AEC representatives
to develop a
preliminary planningstrategy.2 The Director, DNA, Lieute
nant General
aa

NOX EWI

LY

OT

eruUiniiy

i

personal survey of the situation.24 The following week, on
7 September

1972, there was a major conference in Washington,
D.C., attended by
representatives from over a dozen departments and
agencies. The primary

Select target paragraph3