CHAPTER Il, SECTION 1
With the aid of this data it was possible

to estimate the horizonal acceleration due to

wave action and corresponding forces to be expected on proposed test barges. In many cases

these wave forces were more critica] than wind
forces. The wave action and tide data were used
in designing the barge anchorages.

FIELD ENGINEERING.

For a more detailed discussion of survey
and inspection activities, see Sections 1A and
1B respectively.
OFFICE ENGINEERING AND DESIGN. A
design force in the field, which reached a max-

imum of three engineers and seven draftsmen,
wasresponsibile for the production of construct-

ion drawings on all temporary camp facilities;
revisions to Home Office drawings incorporating

for this operation consisted of a Resident Engin-

approved changes, substitutions and additional
User requests; alterations and additions, both

ioning parallel to the Home Office and acting

built” status. Construction camps were not de-

The Field Engineering Division at the site

eer and a staff of assistants set up as a unit incorporating the following four sections, funct-

major and minor, to permanent base camp facilities; and correcting all drawings to an “as-

as a field arm:

signed in the Home Office as in previous Operations in order to relieve that office for the
heavy and tightly scheduled work load on Scientific Stations as well as to utilize field construction experience and to design around stocks
of locally available material.

i. Office Engineering and Design Department.
2. Estimating, Reports and Analytical Department.
3. Survey Department.
4. Inspection and Test Department.

The Engineering Division at the PPG was
responsibile for furnishing complete local engineering supervision and inspection of construction; for making topographic, hydrographic, control and construction surveys, for prepar-

ation of design and drawings for proposed work;
for interpretation of plans and specifications;
for design and approval of alterations and substitutions; for design and estimates on fieldapproved alterations and additions to permanent base camp facilities; for preparation of
record and “as-built”? drawings; for inspection

of construction for compliance with plans and

specifications; for inspecting and testing of con-

struction materials; for submission of reports
and estimates; and for maintaining a complete
file of all drawings and other engineering data.
OPERATION CASTLE, being spread over
two widely separated atolls, presented geographic problems of Engineering control at the seven
construction areas and camps. All drawings and
work orders were issued and all reports were

prepared at the Engineering Office on site Elmer
at Eniwetok where the Resident Engineer and
an Assistant Resident Engineer were located.
Activities of the area inspectors and survey field

parties assigned to sites Elmer, Fred and Ursula
were coordinated through the main office at

During this operation, Field Engineering
Division designed and prepared 863 Field Sketches, 159 miscellaneous drawings and made “‘asbuilt”’ corrections to over 1200 drawings.

The Home Office Engineering Department
furnished Field Engineering with a print and one
reproducible of all drawings made by Home
Office Engineering, which enabled the Field

Reproduction Department to process and make
proper distribution of prints in direct response
to optimum requirements at construction areas.
In previous operations, almost all reproduction

of prints had been accomplished by the Home
Office. Because OPERATION CASTLE was
much larger and more dispersed, the requirements for prints grew to such an extent that in
August 1953 a new Ozalid Super Type “B”

printer was installed at Elmer to handle the

average weekly run of approximately 6000 prints.

During the first half of February 1954, which
was the period of peak load, 63 rolls of printing
paper were used and a total of 8753 prints were
processed in one week during this period. A total
of 106,911 prints were processed during the 18-

week period from October 1953 thru 1 February
1954.

ESTIMATES, REPORTS AND ANALYSES.
As a matter of control, all Field Engin-

eering designs or major revisions to Home Office

designs required the preparation of estimates

for approval. In general, all these estimates were

prepared at Jobsite, as well as analyses in con-

site Elmer. An Assistant Resident Engineer was

nection therewith. Cost control was maintained

on site Tare. Inspection and survey activities
in the Tare, Nan, Fox and Charlie construction
areas were coordinated through the Tare office.
Altogether, the inspection and survey forces

work orders, and completion cost estimates were

assigned to Bikini Atoll, with an office located

accounted for more than 75% of the field engineering manpower because of the dispersed

nature of construction operations.

by a monthly review of accrued costs on all open
submitted in accordance with established pro-

cedure. Preparation of weekly progress reports,

monthly narrative reports, and historical installments was likewise a function of this department. Manpower requirements for reporting
were minimized by utilizing reports made by

Page 2-5

Select target paragraph3