CHAPTER |, SECTION 1
its population. Planning and engineering heretofore described had been modified and extended
by the character of the developing test program,
and construction in place had reflected its then
known requirements. Holmes & Narver Management, delegating most facilities design to Field
Engineering forces, had devoted its Home
Office Engineering staff to close scientific liaison
and priority design of structures as quickly as
criteria became firm.
The early concept of OPERATION CASTLE as it affected the scientific structures program was that it would consist of two ground
shots with zero stations and related photographic and recording stations of the general
magnitude of the Mike shot in OPERATION
IVY. In addition, the decision was made to try
a detonation using a barge anchored in the
lagoon for the zero point. This concept was later
expanded to include three ground zero detona-

tions and three barge shots, and in the fall of

1953 another barge shot was added, making a

total test program of seven shots.

Early in OPERATION CASTLE the H&N
Engineering Division reviewed many of the
major structures used in OPERATION IVY
and, based on this review, prepared advance
estimates of materials required for similar
structures anticipated for OPERATION CASTLE. Procurement of standard materials from
these advance estimates madeit possible to start
a flow of materials to the Atolls prior to completion of design. This technique often made it
possible for the Field forces to start construction

immediately upon receipt of approved design
drawings.

The new design criteria developed at Los

Alamos were transmitted by J-6 Division, and

H&N worked closely at UCRL with their Project
Engineers in development of criteria for the
Laboratory’s construction requirements.
Experience gained during OPERATION
IVY with the 9000-foot plywood tunnel con-

taining a controlled atmosphere envelope for

observations taken on the Mike shot led to a
decision to use pipe arrays in OPERATION
CASTLE between the zero point and recording
stations to accomplish the same general purpose.

The information gained from a UCRLbuilt test section of this pipe served as the basis
for the design of pipe arrays used in each
CASTLE ground shot. The pipe technique imposed rather tight alignment and vacuum retention specifications. Pipe was designed and
fabricated early in the program and subsequent
construction and alignment problems were
successfully solved.
The proposal to use a barge as a zero point
introduced a problem of maintaining stability
but it was eventually determined that a zero
point of this type would be feasible.
Page 1-6

In order to outfit the 500-ton barges it was
necessary to design a barge slip at Elmer with a
traveling gantry crane which could be used for
construction of the barge superstructure as well
as for final installation of equipment by the
Users. In addition, it was necessary to design
an assembly area at Elmer wherecritical components might be stored and eventually assembled and moved onto the barges. This area incorporated facilities provided in previous operations by the USS Curtiss.
Organizing the test structures construction
phase of OPERATION CASTLE required a
considerable amount of logistical planning because of the large area over which the construction activities were conducted. In order to use as
few men as possible on Bikini Atoll and to avoid
duplication of facilities, it was decided that all
materials would be shipped through the Elmer
central warehousing and accounting facilities,
and that only a limited warehousing activity
would be set up at Tare to handle construction
in that area and to act as a redistribution point
for materials destined to other sites in the Bikini
Lagoon. It was planned that the only exception to this would be those items, such as H-beam
steel piling, structural steel, and equipment,

which were of such size and of such an easily
identifiable nature that logically they should
be discharged at Tare. The assignment of an
LST by TG 7.3 as the primary means of transporting materials and equipment between the
two Atolls made it necessary to carefully evaluate in advance the needs for construction
equipment in order that infrequent trips of a
landing ship dock (floating drydock) might be
used to transport equipment such as cranes
which cannot be carried on an LST without
dismantling.
One of the main construction problems involved in a program of this magnitude and
compressed time tables was that of scheduling
materials to avoid delays in the program. The
normal procurement and shipping time on materials, and particularly on fabricated equipment
and structures, was three to four months. Real-

izing that this had to be shortened for those
Stations which were designed late in the program, it was necessary to take unusual action
in all phases of the supply process. For example,
in order to expedite fabrication for Zero Stations
designed late in the program, it was necessary
to obtain a line drawing from Engineering prior
to actual design, and from this drawing the
Procurement Department canvassed suppliers
to determine where material was available, and
time-and-material-type contracts were awarded
based upon these forecasts. This succeeded in
placing a hold on the material and allocating
time in vendors’ plants. As designs were firmed
up, the vendors were allowed to proceed with
fabrication, and by expediting movement of

Select target paragraph3