CHAPTER |, SECTION 1
activity. The base facilities considered to be
permanent for the Pacific Proving Ground are
located on sites Elmer and Fred at Eniwetok
Atoll. In order to provide accommodations for
the anticipated population, including a new peak
high of 3,000 men on Fred, it was determined
that certain changes would have to be made to
existing facilities. On Elmer these changes consisted of: additions to the laundry and mess
hall, an engineering wing on the administration
building, a personnel wing for the administration
building, new barracks, an additional 1000 KW
generator in the power house, additional distill-

ation equipment, and a general revision to the
power supply and distribution systems of both
sites, including a submarine power cable be-

tween Elmer and Fred.

On site Fred, Eniwetok Island, the amount
of actual additional facilities required was not

agreed upon until rather late in the program, and
during the summer and fall of 1953 this phase
of the work assumed larger proportions. An important element affecting the work load was
the decision to move the base of air operations

from Kwajalein, where it had been in previous
tests, to site Fred at Eniwetok. Because of this
decision, it was necessary to expand the facil-

ities; to improve the airstrip paving from the
standpoint of both impact load and area; to

furnish additional parking area, a decontamination pad, additional warehouse buildings; and

to augment the electrical distribution system
to that area. Task Group 7.2 required addit-

ional recreational facilities, administrative buildings, and general improvement in many of the

was designed, requiring a minimum cost for
installation, to provide maximum_ protection
against wave action resulting from storms. This

wall was extended only in the areas which were
observed to be most vulnerable and where existing facilities had suffered the most damage

during “Typhoon Hester.”
The engineering
design of airport facilities was coordinated with
the Air Force in order that their needs for handling many types of aircraft during the Operation
would be met. Approximately two-thirds of the

airstrip was paved, including the taxiways which

were provided, and improvements to the existing facilities were made, such as providing a
concrete floor for the B-50 hangar. A new con-

crete pad was designed to provide an area for
washing down contaminated planes.
Construction of the additional facilities on
Elmer, at Eniwetok, was accomplished in the
summerand fall of 1953 as time could be spared
from the scientific program. Construction work
proceeded without unusual incident. Site Fred

construction was coordinated with the priorities
established by the Using Agencies, and in many
cases construction schedules were made contingent upon help supplied by TG 7.2 in the erection of buildings and other work requiring un-

skilled labor. Many prefabricated structures that
had formerly been at Kwajalein were re-erected,

using a large percentage of TG 7.2 labor. The
paving of the airstrip and related items of work
were correlated with air operations and were

accomplished with a minimum of interruption
to air traffic.

camp areas. In addition, it became necessary

Construction work in this period progressed
without abnormal incident, though the rather

Also affecting the Eniwetok work load was

tion of work orders, especially those involving

occurred in December 1953; these storms made

burden on the scheduled construction at a time
when the scientific program was at its peak,
with the result that many items of work were

to increase the water supply.

“Typhoon Hester” which occurred on 29 December, 1952, and “Typhoon Doris’ which

necessary the rehabilitation of many structures
and areas, and pointed up the need for additional shore protection from storms, particularly
on site Fred. This action was taken. Buildings
in general, appeared adequate for storm wind

pressures.

To engineer the added facilities on both
Elmer and Fred, maximum use was made of

prefabricated buildings for such structures as
the laundry, administration buildings, barracks,
and mess hall. Existing prefabricated buildings

had proven their adaptability to this type of
use and had a fine record for withstanding the
climatic conditions, including the high winds
encountered during typhoons. The new warehouses at both sites were of steel frame with

aluminum siding. This was considered to be
the most economical type of building suitable
for warehouse structures in that climate. To
resolve the problem of beach erosion on the

ocean side of Fred, a seawall of poured concrete

heavy work load, resulting from an accumula-

preliminary electrical work requests, placed a

not accomplished as promptly as would have

been the case under normal conditions. The in-

stallation of a submarine power cable between

the two sites solved a power problem and made
it possible to supply site Fred with approximately 1000 KW from the Elmer power plant.
The Fred power plant was then used as a
source of standby power and, primarily, for
furnishing power to the distillation plant during
peak loads.
The site plans for all camps are shown in

Figures 1-3 through 1-9 at the end of this

chapter.

The scientific structures program, intimately identified with the primary mission of the
proving ground development and always crucial
to the logistics and completion schedule of the

Contractor, had been gradually emerging con-

currently with the design and construction of
base facilities to support the test operation and
Page 1-5

Select target paragraph3