CHAPTER !, SECTION 1
When the Contractor assumed the responsibility for radiological safety at the Proving
Ground, radioactivity levels were such as
to require film badges to be worn byall personnel at most work sites in Bikini Atoll and a
number of sites in Eniwetok Atoll. Rigid RadSafe control and decontamination by removal
of four to eight inches of the contaminated
area surfaces permitted operations to proceed
without serious threat of overexposure through-

out the construction phase. With the firing of
the REDWINGshots, practically all sites at
Eniwetok Atoll and those at Bikini Atoll,
except Nan, became contaminated.

Recovery

and roll-up missions were accomplished as required and a few men received cumulative
dosages above the standard of 3900 mr within
a thirteen week period. The overexposures prior
to the Tewa event were not excessive. As a result of this event held in Bikini Atoll on 21
July 1956, fall-out occurred at the permanent
base camps on Eniwetok Atoll at 1500 hours
on that date and continued until 0800 hours
on 22 July at which time the reading above

background was 110 mr/hr. This was the cause
of considerable concern as a large number of
personnel received dosages above the established
maximum and might have to be evacuated.
Therefore, on 24 July, CJTF-7 authorized an

increase in the operational tolerance from 3.9r
to 7r and the Director, Test Division later
authorized Holmes & Narver to retain, during

the post operational period, those personnel who
had exceeded the 3.9r limit for a thirteen week
period provided the average quarterly dose for
the last three quarters of 1956 would be less than
3.9r. A check made on 27 July revealed that approximately 100 men then at the Jobsite had
received dosages between 3.9r and 8.0r, and

there was a possibility that this number would be
substantially increased. The change in permissable exposure limitations relieved an unsatis-

factory situation. The termination, because of
radiation exposures, of a large number of men

whose contracts had not been completed could

have caused strong resentment and undesirable

publicity. By keeping the men on the job the
possibility of ensuing claims was reduced.
Also, the possibility of the rehire of key personnel was greater. The responsibility of the
operational control for radiological safety at the
Proving Ground reverted to the Contractor on

the clearance of personnel. Close liaison was essential between the Contractor and AEC security representatives for the establishment of workable procedures to resolve the problems arising
from these requirements. Consideration was
given to overcoming measures which slowed up

action in assignment of personnel because of
clearance requirements. These included changes
in the authority for issuance of travel orders by
concurrence of CJTF-7 and Cincpac. This eliminated time losses by the delegation of authority
to certain contractual employees to execute
functions formerly performed by the Port Control Director, Long Beach Naval Station. In

addition, a modified clearance program permitted the assignment of Good Security Risk
(GSR) personnel to the PPG. The use of GSR
permitted earlier assignments for the build-up
phase. Processing for GSR during peak activity
averaged eight days, whereas the time for a
Q averaged 94 days; for an L, 52 days; for a
P, 43 days; and a QR, 24 days. As the P ap-

proval and GSR certification did not authorize

access to information classified ‘Restricted
Data’, a cutoff date of 15 March 1956 - after

which all personnel at Jobsite had to be either
“Q” or “L” cleared - was established. Because
of pressing work, this was delayed until 7 April

with permission to retain P and GSR personnel

at Fred until 20 April 1956. During the period
from 1 July 1954 through 30 June 1956, there
were 1,228 Q requested, 865 granted; 2,660 L
requested, 2,197 granted; 865 P requested, 657

granted; 1,692 GSR requested, 1,386 granted;
1,388 QR requested, 1,335 granted.

The responsibility for the operation of the
Pass and Badge Office involving the issuance
of identification media was first assumed on 1

July 1955. Policy direction of this office was retained by the AEC.
Dependable teletype communications between Eniwetok, Hawaii and the Continental
United States were provided through the U.S.
Army “ACAN” world-wide teletype network
augmented by a Los Alamos-Eniwetok circuit.
The Los Alamoscircuit provided the Contractor
an alternate route when the ACAN net was
jammed, which frequently occurred during the
operational period. Radio-phone service between

6 August upon the departure of TU-7 of TG 7.1.
The seriousness of the situation at Elmer was
well recognized by Management. Decontami-

the Home Office and Jobsite was first initiated
on 6 December 1955 but because of security
requirements and transmission difficulties this
system was seldom used. Prior to the activation

tinued until the radioactive level presents no

tion link between Bikini and Eniwetok consisted

nation and rigid control measures will be con-

serious problem. This is expected to be about
1 October 1956.

of the VHF interatoll system, the communica-

of an HF radio telephone and a teletype circuit.
During the build-up phase, traffic became heavy

The security requirements of the Atomic

and delays in communication resulted but with
the activation of the VHF circuits, satis-

concerning unauthorized disclosure of information, the safeguarding of classified material and

good telephone service was maintained. During
the build-up phases, exchanges were operated

Energy Commission included specific provisions

Page 1-24

factory service was provided. Within each atoll,

Select target paragraph3