CHAPTER |, SECTION 1

wt

Figure 1-8.

|

~

~~S

Tanker Approaching Deep Water Pier - Elmer

tion worsened. As MATScapabilities for breaking the jam in cargo could not be clearly de-

termined, an investigation was madeas to availability of commercial charter planes, with the
thought that these might be used as an emergency means of reducing the backlog. This was

found feasible, but as the military facilities were

thereafter augmented rapidly, the charter planes
were not needed. The allocation of space for
emergency airlift of heavy tonnages of Contractor’s cargo (318 tons during February,

materials were transshipped to construction sites
in small marine craft operated by the Contractor. For construction at miscellaneous sites
away from established camps, boat schedules
often had to be arranged in accordance with

prevailing tidal conditions. This movement of
material from its original point of receipt at
Elmer to its final location was always critical
due to the tight construction schedule.

construction program required a considerable

On 7 March 1955, the Atomic Energy Commission, in response to requests from the High
Commissioner of the U.S. Trust Territories for
aid to the ex-Bikini people, authorized the construction of a small camp at Jaluit Atoll and
radio stations for Jaluit, Majuro and Kili. Because of inclement weather and resulting un-

possible and to avoid duplication of facilities,

materials for the Kili project, it was deleted
from the program. For the support of REDWING, weather stations were authorized in

March and April 1956) was an important fac-

tor in meeting construction schedules and suc-

cessfully completing Operation REDWING.

Organizing the scientific test structures

amount of on-site logistic planning because of
the large area over which construction activities
were conducted. In order to use as few men as

all materials and equipment were first received

in the Elmer central warehousing and accounting

facilities and then transshipped to the more
limited facilities set up in Bikini Atoll. The
full-time assignment of one LST and the parttime assignment of a second permitted estab-

lishing a shuttle service between Bikini and

Eniwetok Atolls for the primary means of transporting equipment and materials. In each atoll,

favorable conditions for landing construction

September 1955 for construction on Kapingamarangi, Kusaie, Rongerik, and Tarawa. This

construction was scheduled in two phases: the
structures and facilities were provided in the
first phase, and the equipment was installed
in the second phase. Construction of the first
phase of these projects was nearing completion
in December 1955 when requirements for offatoll scientific projects became firm. These pro-

Page 1-19

Select target paragraph3