CHAPTER I, SECTION 1
was essential to check possible delays. The availability of drawings, materials, manpower in required categories, special equipment, and the
movement of the materials to and within the
site hadto be closely watched in order to assure
orderly construction and the progress required.

Sacrifices by scientific project personnel in
shortening beneficial occupancy time, and in
foregoing some pre-test preparations assisted
materially in readying the stations for the first

test as scheduled.

Extensive construction activities were re-

quired on reefs, which had to be accomplished
with all the disadvantages inherent to working
in sea water of varying depths. Man-made
islands and causeways were among the major

items of this type of construction. The design
of these called for construction of bulkheads

of three-inch timber supported on 60-pound

rails driven on five-foot centers; the backfill

was of available beach sand and
Tidal conditions had to be watched
frequent shutdowns were necessary.
ment had to be serviced frequently,

reef coral.
closely and
The equipand at the

VHF radio transmission between Eniwetok and
Bikini Atolls. Thereafter, for the primary radio
link between these Atolls, a multiple channel
VHF system was designed with the terminals
at Elmer, Nan and in the USS Curtiss and
USNS Ainsworth. Joint Task Force SEVEN
arranged for the loan of AN-TRC-24 multi-

channel radio equipment for use in this system,
and the antennas and other appurtenances were
obtained by purchase. A change in frequency

assignments necessitated the redesign of two

of the four antennas being manufactured. As a

result, delivery of the antennas was delayed

three weeks and the system was not activated

until 28 April 1956. Prior to this activation, the
existing HF telephone channel became over-

loaded and delays as long as three hours were

experienced in completing calls. However, few
difficulties were experienced after the activation
of the VHF system, which was adequate in all
respects and very effective in providing a reliable interatoll communication system.

drained, flushed, and refilled. Men tired quickly,
and even with the most thorough preventive

In planning the submarine cable systems,
a complete survey of existing cables was made
early in the program. Preliminary estimates of
requirements were made, which included the
replacement of faulty cables and the estimated

impaired the life of equipment. Weather was an
important element. In December 1955, the

half million feet of cable and necessary splice
boxes were initially ordered; additional quan-

seas, which periodically occur in this area.
These high seas caused some damage to the

and a total of 814,000 feet was eventually laid
in both Atolls. The laying of this cable was
accomplished without unusual incident. However there were various incidents of damage to

end of each working day,all oil cases had to be

maintenance measuressalt water action seriously

Proving Ground was subject to especially high

construction-in-place of the man-made islands
and causeways. This occurred during the period
in which the over-all construction schedule was

extremely tight. Extraordinary action was taken
to speed the flow of personnel to the Jobsite;
the damage was repaired and the temporary
setback in construction was overcome without

a serious effect on the over-all progress.

Experience during previous test operations
indicated that the communication facilities for

the PPG-ZI system had to be modified and

expanded. Expansion of the electrical and
other facilities at Fred had increased the interference noise level at that site to such an

extent that it reduced the reliability of the

receiving operations; also, the locations for new
buildings were limited; most critical of all
was the lack of area for antenna fields. This
led to the selection of David for the location

of a new Joint AEC-Military Radio Receiving

cable for additional circuits. Approximately one-

tities were ordered as requirements became firm,

cables by ships’ anchors; the entire system between Elmer and David, and three telephone
and three signal systems off Elmer were dis-

rupted because of damagebyships.

LOGISTICS.
A large volume of equipment and materials

had to be procured and shipped in a limited
time. The normal procurement and shipping
time of material from the States and particularly of fabricated equipment or specially designed assemblies was three to four months.
These lead times had to be drastically shortened
as success in meeting desired completion dates

depended considerably on the movement of material at an accelerated rate. This had to be

accomplished in a stringent material and equip-

the transmitting facilities that remained on Fred

ment market during a period in which demands
from both industry and the consumer were the
greatest in the history of the nation. Aggravating these market conditions were prolonged
strikes in key manufacturing plants, plus ab-

In conjunction with AEC communication
personnel, a series of path proving tests were
conducted which determined the feasibility of

essary to plan for and take unusual action in
all phases of the supply process. Where practi-

Station with camp facilities to support opera-

ting personnel. With the movement of receiving

activities to David, considerable expansion of
could be effected.

Page 1-16

normal weather conditions affecting both manufacturing facilities and transcontinental shipping. In view of these conditions, it was nec-

Select target paragraph3