16
Exploration was made early in the program

to determine suitable sources of coral aggregate,

and from samples tested by the Field Engineering Test Laboratory, possible reef locations
were selected. As the program developed, estimates were made of the yardage of aggregate
anticipated for the various areas and schedules

were established for quarry and crusher opera-

tions. The quarry operations were governed by

the normal difficulties encountered in subaqueous excavations. Frequent shutdowns occurred
because of high tides and wave action. The use
of wagon drills and compressors mounted on
trailers permitted drilling at a much highertide
level than would have been possible if the standard wheel-mounted wagon drills had been used.
To ensure maximum production with a minimum of operational interference-and as an added
safety factor-all blasting was performed after

regular working hours. Stockpiling of aggregate
was both logical and economical. For areas re-

quiring quantities of less than 1,000 cubic yards,

CHAPTER I, SECTION 1
the steel components. Completion of the construction of the towers for Stations 5, 6, and

7 was held in abeyance until after the firing

of the first shot due to the probability of damage. The tower and guy anchor blocks were
provided for these towers, and Station 5 was
built to the 75-foot level. After the first event,
Station 5 was deleted from the program and
construction of Stations 6 and 7 was completed
on schedule - though under rigid Rad-Safe con-

trol because of the widespread radioactive con-

tamination of the area from thefirst event.

The problems resulting from the tight construction schedule are well illustrated by those

that arose in the procurement of materials for,
and in theinstallation of, the pipe arrays. In the
very beginning, procurement difficulties were
encountered in obtaining pipe on acceptable

delivery dates. After considerable canvassing of
steel mills, pipe was found with acceptable delivery dates but a decision had to be made
to accept certain sizes which were not in rigid

aggregate was provided from the stockpiles at

accordance with the specifications but were considered usable. Materials for the support sys-

crete required at each site; these plants were

available materials and fabrication at the Job-

main production plants. Main batch plant locations were determined by the quantity of conestablished at Elmer, Fred, Yvonne, Ursula,

Gene and Janet in Eniwetok Atoll, and at Nan,
Tare, Fox and Charlie in Bikini Atoll. Concrete

wasdelivered to the construction sites in transitmix trucks. Small concrete requirements, such
as for anchor blocks and small instrument
mounts, were precast at Elmer or Nan or were
poured from small mixers. The amount of concrete poured monthly is shown in Figure 2-25,
Chapter II. From 1 July 1954 through 1 May
1956, when concrete pouring for scientific structures was practically at an end, 210,000 sacks

of cement and 2,757 tons of reinforcing steel
had been used.

The shot towers were designed to permit
prefabrication of steel components in 25-foot
modules and erection on the basis of 100-foot
increments to a maximum of 300 feet. This provided for the 200-and 300-foot towers in one
design, and simplified steel erection. To assure the proper matching of appropriate parts, a
75-foot section of a typical tower was first
erected from parts selected at random by a Contractor’s inspector at the fabricator’s plant. Because of the time element involved, the drawings
of the tower and guy anchor footings were re-

leased prior to approval of the completed tower
design. The site location of some towers required

that several guy anchor blocks be located on
reefs. In such cases a pile foundation was mandatory. This work, and the pouring of the concrete anchor blocks, was scheduled in accordance with tidal conditions and measures had
to

be

taken

to

prevent

loss

of

cement

through wave action. The early release of draw-

ings for the footings permitted steel erection

to be undertaken immediately upon receipt of

tem were late in arriving and substitution of
site made it possible to maintain progress on

this phase without a serious loss of time. Many
of the components of the alignment system
had to be rushed by air, and there was one

case of jettisoning of urgently needed items by
a plane in distress. An exceptionally high degree of cleanliness and freedom from rust in

the interior of the pipe was required. Special
measures taken before overseas shipment to

ensure this cleanliness and rust freeness, accomplished during the period of record rainfall in
California, proved inadequate and processing
of the pipes had to be repeated at Jobsite. To accomplish this, it was necessary
to airlift 12 tons of grit. Improvisations and

repairs had to be effected at the Jobsite to the
project-furnished vacuum pumps to make them
operable. Last-minute revisions in the location

of a few pipes were required. By concentrating
the available competent craftsmen, using over-

time and shift work, and with the acquisition
of additional welding equipment on a loan basis

from Military Agencies at Kwajalein and Eniwetok, the pipe arrays were readied in time, and

were integrated into the test program without
adjustment.

The island of Yvonne, approximately 8,700
feet long with an average width of 550 feet,
was thesite of 191 scientific stations. Complexity
was introduced by locating so many stations
in such a small area, and by the multiplicity of
the changes in location and requirements for
the stations and the late dates at which these
were received. Many of the stations had to
be completed as scheduled since they were
vitally required for the first test. Continuous
surveillance of all factors affecting construction
Page 1-15

Select target paragraph3