CHAPTER 1, SECTION 1
A system of advance material estimates
made it possible to initiate procurement of selected materials and equipment at an early

stage in the Operation. Construction items of
common usage were purchased and shipped to
Jobsite as stockpile or warehouse stock. This
was accomplished before the completion of, and
in many cases before the start of, working draw-

ings. Quantities were determined on the basis

of previous usage of similar construction items.
As drawings were released, the material-takeoff and bills of material provided for the al-

location of available materials to specific construction.

The Estimated Operations Schedule for test
facilities was first issued on 14 July 1955. Criteria were not firm at this time but a realistic

attempt was made to schedule a date when they

would be available and the engineering completed. The schedule for procurement was based

on anticipated design, experience and judgement. The construction period was determined
on the basis of the estimated productive labor

required, along with the dates anticipated for

release of drawings and receipt of materials. For
the effective follow-up of this schedule, key information concerning status of design, material
deliveries, and construction progress was closely
watched in order to ascertain which critical

items required special handling.

To incorporate the latest changes in weap-

on design or refinements in instrumentation in-

to the test program, changes were made by
scientific personnel in the number of events,
methods of instrumentation, location of stations,
and shot sequence. As a result, firm criteria

were not received as early as anticipated. Each
addition or change had to be adapted to site

planning or other possible conflicting objectives.
To cope with changing scientific requirements,
the Operations Schedule had to be reviewed
periodically and revised so that it reflected the
latest information regarding the various as-

pects of design, procurement, and construction.

Round-table discussions between representatives

of the Contractor, AEC, and other agencies in-

volved were most beneficial in resolving relevant

problems. At a discussion held in Albuquerque

indicated that the completion dates requested
for several stations could not be met. These
completion dates were re-scheduled, and it was
later determined that the test programs could
be adjusted to accommodate these revised
ates.

At this period in the Operation the shotisland camps and other temporary base facilities were practically complete, but little construction progress had been made on thescientific structures program and on 15 October only

two per cent completion could be reported. However, design drawings had just been previously
released for the construction of three small islands on the Dog-Charlie reef, two causeways
and an island off Yvonne, and an island causeway off Sally. With the further release of many
drawings in November and December 1955, construction activities on scientific test facilities

increased rapidly.

The situation with respect to the possibility
of completing many of the scientific stations,
particularly on Yvonne for the first event, be-

came extremely critical by November 1955. To
evaluate the prospect thoroughly, a conference
was held at Eniwetok early in December, dur-

ing which the Director, Division of Military Application, AEC; Director, J Division, LASL;

Deputy Director, Test Division, AEC; and
Manager, Construction Division, H&N, visited
all construction sites and re-evaluated procure-

ment and construction schedules with the re-

sult that it appeared impossible to meet the

schedules last established. Although there were
incipient shortages in certain labor classifications, the problem of material delivery was paramount and could not be solved underthe hitherto allocated air and surface lift.

At this time both the Director, DMA and
Director, J Division, stressed the compelling importance of making every practicable effort to
meet the required operational readiness dates
through the expediting of engineering, procurement, and construction, to the extent of all
necessary overtime, premium pay to vendors for
faster delivery of fabricated materials and equipment, procurement of materials and equipment

on 19 September 1955, the latest revision of
this Schedule was reviewed. At that time the

on an “off-the-shelf”? basis wherever they could
be located, and the airlift of any items capable

LASL and DOD programs had been firmed

construction schedules. In turn, AEC and CJTF
SEVEN would do everything in their power to

design for the UCRL program appeared well
advanced; however, little of the criteria for the

of being airlifted if such was required to meet

with the result that this design was only 10%
complete. Because of the great number of revisions and additions to design criteria in Sep-

The Director, J Division, agreed to delay,

revise this schedule accordingly. On 4 Novem-

These principles were confirmed and re-empha-

the Contractor’s Home Office with the Deputy
Director, Test Division, and representatives of
the scientific laboratories. This revised schedule

the Manager, SFOO. In the subsequent months,
airlift tonnage was greatly increased and the

tember and October 1955, it was necessary to
ber 1955, this latest schedule was reviewed in

Page 1-12

obtain extra airlift, and surface lift as required.
wherever possible, the station occupancy for set-

ting up and checking out the instrumentation.

sized in a letter dated 22 December 1955 from
frequency of ship sailings was stepped up. Con-

Select target paragraph3