CHAPTER Ill, SECTION 6

WING in early 1955, the tempo of activities

increased rapidly and reached peak activity
in the latter months of 1955 and early months

of 1956. On-the-job training of new personnel
was necessary since those persons experienced

in buying, expediting, and shipping, particularly

under governmental procedures, were not readily
available.

As plans and drawings for REDWING test

facilities became available late in 1955, it was

apparent that a large volume of equipment and
material would have to be procured and shipped

in a limited time in order to meet established
construction schedules. The normal lead time
on materials, particularly for specially-designed
or fabricated items, was three to four months.

However, it was quite evident that this much
time could not be allowed, and in a market
in which the demands from industry were the
greatest in the history of the nation. this some-

times became a serious problem. In addition,
devestating floods in the Northeastern United

States and in Northern Califomia and Oregon,

plus prolonged strikes in some key manufactur-

ing plants, aggravated the situation.
Within

the

specially-fabricated

category

were such items as the rollers for the vacuum

pipe support system, blast doors, dehumidify-

ing units, many small generating units, control
panels, and other control appurtenances. Electrical items presented a proportionally larger

problem than did those of other items because
of the market condition in the electrical field

and because many of these items required special factory orders to meet design specifications.

In view of these conditions, 1t was necessary
to plan for and take unusual action in many

phases of the procurement process. Vendors had
to be canvassed in advance of requisitioning
to determine where materials were available

and which vendors could be depended upon to
keep delivery promises. To break into their
backlog of orders and to obtain precedence in
delivery, firms had to be convinced of the importance of the order. Many fabricators willingly set aside their normal production schedules and made men and materials available when

informed that the work was of high priority
for the Atomic Energy Commission. In some

cases it was necessary to ask priority assistance
from the Supply Office of the Albuquerque
Operations Office through Defense Order Priorities.

to ensure acceptable deliveries, but in all such
cases prior approval of design or operating
personnel was obtained. Overtime for certain
fabricators and on-continent premium

trans-

portation (air freight, air or railway express)
were authorized. All such expediting action was
taken only after the need for the item became
so critical that any delay in deliveries would
jeopardize completion dates of vital facilities.
The procurement of pipe and other components for the vacuum pipe arrays was one of

the most complex of the problems encountered; it is cited here as an example. After
the purchase order for the pipe had been
awarded, it was found that the vendor could
not keep his promised delivery date. Various
steel mills were then canvassed and pipes were
located that could be delivered on acceptable
dates; however, a decision had to be made to
accept certain sizes that were not in accordance with the rigid specifications but that were
considered useable. The rollers for the support
system also gave indication of late delivery.
With the cooperation of the vendor and through
direct contact with the factory in Atlanta, Georgia, the quoted delivery dates were improved

and certain items were rescheduled to effect
delivery of the sizes most urgently required.
The cross-country shipments of these rollers
were closely followed and as a result, were moved

to the export packers in much less time than
would normally be required. One overseas air
shipment of the rollers was jettisoned from a
plane in distress, and hurried replacements had
to be ordered from the factory. A separate purchase order contract was let to process the

pipes before shipment to the Jobsite to ensure
their arrival with the high degree of cleanliness
and rust freeness required. Inside surfaces were
grit-blasted, cleaned with acetone, and then

blown with hot air, This work had to be accomplished during a period of record rainfall.
After they were thoroughly cleaned, the pipes
were fitted internally with a square cardboarc
paper tube impregnated with a rust inhibite

and then capped for shipment. When the pipes
were opened at Jobsite, it was found that some
rust had set in and it was necessary to reproces

them in the field. Grit for blasting had to b
rushed by airlift in order to have the pipes ready
in time so that construction schedules could be
essentially met.

Pertinent statistics covering procurement

activities were as shown in Table No. 3-4.

As time hecame the all-important factor,

Where export packing was not provid
by the vendor, it was accomplished either unaer
contract with Richmond Export Services (FY

sary to check delays. Assistance was given to

or by the Holmes & Narver warehouse in J] 5
Angeles, California. The methods and proceduies
used in handling, packing, and exporting con-

almost daily .oniact was maintained with the
various vendors iabricating critical items; onthe-spot inspection provided the means neces-

some vendors in obtaining parts from other
suppliers or factories. Substitutions were made
Page 3-26

1954) and Pacific Ports Industries (FY 195. °,

Select target paragraph3