CHAPTER Ill, SECTIONS 1 and 2
10.

Provision for and management of
service and supply facilities needed to
make the project and its personnelself-

sustaining.

11.

Maintenance of improvements already
in existence at the Proving Ground.

The Chief of Operations represented the
Project Manager in correlating various Home
Office activities with the field operations to ensure that Jobsite operations were geared to
Home Office planning. Of particular importance
in this respect was the supervision of activities
directly affecting schedules. He was, therefore,
responsible for the preparation of advance material estimates and bills of material, issuance
of all requisitions, and checking inventories for

the possible use of materials in long supply. All
requisitions were screened to ensure that the
materials or equipment ordered were justifiable
and were being purchased in accordance with
Commission and Contractor policies. An inspection force directly under the Chief of Operations ensured that materials, supplies and equipment being supplied were in accordance with
purchase order specifications or that deviations
from design specifications were acceptable to

Engineering or Operating personnel as appli-

cable. For the effective follow-up of schedules,
all key information was funneled to the Home
Office Operations Department (under the Chief
of Operations) where it was assembled and recorded. The essential data regarding scheduled
and actual progress of design, procurement, and
construction were watched closely and, when

necessary, priorities were established and expediting action taken. This included priority in
overseas water transportation and the use of
airlift for critical cargo.
The Chief of Operations kept the Project
Manager informed of the developments in the
field so that on-continent services could be coordinated to meet field requirements. This coordination included the need for revisions in
schedules and necessary liaison with the AEC

when the desired completion dates could not
be met. During the planning and build-up stages,
the Chief of Operations remained in the Home
Office, but as plans matured and field operational activities increased in tempo, he transferred to Jobsite for the period of peak activity.
The Chief of Operations supervised operations in the field through the Resident Manager.
Due to the magnitude of Operation REDWING,
three Assistant Resident Managers were assigned during the peak of activity. The Resident
Manager controlled field activities through Division Heads as shown in Jobsite Organization
Chart Figure 3- 2.
The solution of problems encountered during previous test operations led the AEC to
assign the Contractor additional functional responsibilities in connection with Proving Ground
operations. These additional responsibilities involved photography, pass and badge control,
stevedoring, radiological safety and communications. To administer these added responsibilities properly, a regrouping and reassignment
of divisional duties within the Jobsite organization was effected and a new Administration
Division was established. The details with respect to implementing the Jobsite organization
for the assumption of these added responsibilities are discussed in appropriate succeeding sections of this chapter.
The Chief Project Engineer was in charge
of all engineering phases of the project, such
as funneling engineering requirements into proper channels within the H&N organization and
acting as a final source of technical information
for both AEC and H&N managementpersonnel.
The procedural technique involved in the engineering phase has been previously discussed in
Section I of ChapterII.
A detailed description of the mechanics of
administrative control covering Accounting, Estimating, Industrial Relations, Safety, Procurement and Security is related in succeeding sections of this chapter.

SECTION 2
ACCOUNTING
For accounting purposes, Operation CAS-

TLE ended 30 June 1954; REDWING was

initiated on 1 July 1954 and ended on 30

August 1956.

Supplemental Agreement to Contract AT
(29-2)-20, Modification No. 38, dated 23 September 1954, effective 1 July 1954, was received
by the Contractor on 6 October 1954. The terms
and conditions of Modification No. 38, Article
Page 3-2

No. X, briefly set forth the Commission’s position as to the Accounting Department’s requirements and responsibilities. Accounting records,
books of account, systems of accounting, internal
control, auditing, etc., were to conform to generally accepted accounting principles satisfactory to the Commission. Accounting records
under the Contract were to be maintained as
a separate and distinct set of accounts showing

Select target paragraph3