CHAPTER Ii, SECTION 3
Stations 311.01, and .02 and .03 were also
steel trussed with corrugated asbestos roofs, but
the siding was 8-inch thick reinforced concrete
with a 7’ high continuous opening 7’ off the
ground. The ends of the buildings were left
open.
On 18 December 1955, a combination of

high tides and a storm caused inundation in the
vicinity of Station 311.03, Dog. All of the work
accomplished on the station to date, even to
the stakeouts, was lost.

The criteria covering the size of the manmade islands and the location of the stations
were furnished by the User. A description of
the islands and problems involved in their con-

struction are found in this report under the sub-

heading of Man-MadeIslands.

A total of 55 cubic yards of concrete at an
average 28-day strength of 5,300 psi was poured

for Station 310.01, 55 cubic yards at 3,800 psi
for 310.02, 62% cubic yards at 5,000 psi for

310.03, 180 cubic yards at 4,600 psi for 311.01,

204 cubic yards at 3,200 psi for 311.02 and

Figure 2-57. Station 312.04 Form for Precasting

167% cubic yards at 4,025 psi for 311.03.

measures were required to prevent leakage. Since
the finished grade on the man-madeislands was
only two feet above the high water line, a portion of the structure was constantly submerged
in saturated soil. This posed two problems:
first, the buildings might necessitate cassion

shafts of sufficient size to accommodate construction and heavy enough to remain submerged when set in place; secondly, was the need

for sealing the porous concrete from the water

~—

'

Oecower Ee

Figure 2-56.

STATIONS:

PURPOSE:
SITES:

USER:

Stations 311.03 with 313.06

in Foreground

312.01 thru 312.04

Instrument Shelters
Man-MadeIslands

(Charlie-Dog Reef)
(312.01-312.03) Dog

312.04

DoD Program 3 Project

PARTICIPATION: 18
CONSTRUCTION: 2-13-56/4-20-56
OCCUPANCY:
4-11-56
These stations were reinforced concrete
buildings 10’ x 15’x 10 high with walls and a
floor slab 10” thick designed to withstand expected overpressures. The tops of the structures

were 2’ above finished or natural grade. Proper
Page 2-72

that would seep in the sides and bottoms of the
building. The best solution appeared to be precasting each building and then setting it in place.
The structures were therefore designed to be as
light as possible and yet strong enough to withstand expected pressures. The bottoms and
about four feet of the sides were encased in 1%”

steel jackets with watertight seams. The jacket
served in part as the outside form for the con-

crete pour. The entire form was erected adjacent to the excavations. At Dog, an attempt
was made to lower the form with only the floor
precast. It floated and had to be raised; walls
were added, which provided the weight necessary to help the structure set in place. Precasting of the floor slabs for the stations on the
man-made islands was also necessary.
Three 8-inch pipe vents extended through
the roof and at each end of the battery room,
and one was installed opposite the shelter entrance. Blank flanges on each vent covered the
openings prior to the experiment. The entrance
was a 2’-6” square hatch with a blast resistant,
watertight, steel cover.
Power to each station was supplied by a
portable 25 KW diesel-driven generator which

Select target paragraph3