CHAPTER 11, SECTION 3
USER:
DOD-2
PARTICIPATION: 13, 18 and 22

CONSTRUCTION: 3-28-56/4-18-56

OCCUPANCY:

4-13-56

Station 271 was a User-furnished steel failout collector tower set on concrete piers. The
tower was delivered to Nan by YFNABbarge,
upon which the tower had been completely

assembled. The tower was later placed on an

LCU and transported to How.
STATIONS:

310.01, .02 and .03,

311.01, .02 and .03
Loading and response of
Structures
Man-MadeIslands,

PURPOSE:
SITES:

Charlie-Dog Reef: Except
311.03 on Dog

USER:
DOD
PARTICIPATION: 18
CONSTRUCTION: 12-12-55/4-27-56
Figure 2-53.

Station 268.22 - 95% Complete

STATIONS:
PURPOSE:
SITES:

269.01 thru 269.04
Base Surge Measurements
Fox, George, Oboe and
Uncle
USER:
DOD-2
PARTICIPATION: 11, 13, 18 and 22
CONSTRUCTION: 3-3-56/4-12-56
OCCUPANCY:
4-12-56
These stations were two 4’ x 4’ x 2’ deep
concrete foundations in each of which one 4”
diameter 3’ high pipe column was embedded.
A 3’ x 3’ x 2’ deep plate steel box was on the
same center line as the two concrete pipe foundations. Conduit embedded in the concrete connected this box to each pipe column. Userfurnished equipment was placed in the steel box
and on top of the pipe columns. A minus-1minute timing signal was required. Each station
contained 2-1/2 cubic yards of concrete.
STATIONS:

270.05 thru 270.08

SITES:

Wilma, Bruce, LeRoy and

PURPOSE:

Fall-out Collectors and
Cessation Monitors

Mack

USER:
DOD-2
PARTICIPATION: 13, 18 and 22

Three 40’ x 40’ and three 40’ x 80’ steel
structures were built. The User furnished
drawings, steel schedules, and special provisions
covering these structures, which were of the

identical type used for Operation Teapot in
Nevada. All materials and equipment, other
than the structural steel and the test apparatus,
were furnished by the Contractor. The siding
and roofing were the same type and had the
arrangement and attachment as in the build-

ings utilized

during

Teapot.

The locations

were the following distances from Station 18 to

the working point of the building: 310.01 (40’
x 40’) 20,500 feet; 310.02 (40° x40’) 24,000
feet; 310.03 (40 x 40’) 29,000 feet; 311.01 (40’
x 80’) 24,000 feet; and 311.02 (40’x 80)
29,000 feet; and 311.03 (40 x 80’) 35,600 feet.

The area in front of Station 311.03 was cleared
of debris and any rock more than 1-1/2 inches
in diameter.
The man-made islands had an elevation of
plus 9.5 feet which was sufficient in height for
protection against normal wave action. The

leading edges of the man-made islands were

rounded on a radius of approximately 2’ from
high tide level to the normal elevation.
The steel columns of each station within

this series rested on concrete piers which extended through the island fill and 6” into the
coral. The piers were interconnected by means
of foundation walls extending down to coral.

These stations were User-located, furnished,
and installed measuring devices.

During construction, it was found impractical
to keep the foundation walls keyed continuously
into the coral because of its hardness.

STATION:
PURPOSE:
SITE:

A decision was reached that adequate reaction would be obtained by keying only the
pier footings into the coral and then driving

Page 2-70

271
Fall-out Collector
How

Select target paragraph3