FY
BUDGET
U.S. DEPARTMENT OF ENERGY
PACIFIC AREA SUPPORT OFFICE
Holmes & Narver, Inc.
Energy Support Division

Pacific Operations

Contractor

FIELD TASK PROPOSAL/AGREEMENT
(M Dollars)

Date:

April 23, 1982

Program 35-HA-00-00

Schedule 45 (continued)

The 30 KW Generator will serve as a back-up for generators at all sites, By FY 1984 several of those in
use will be unreliable and uneconomical to maintain. Fuel efficient and reliable generators are essential
for communications and life support at the remote sites.
The four (4) Pickup Trucks are expected to be obtained through the Excess Program. The 14K estimate is
considered a reasonable amount to cover repair work and transportation costs, The units would replace
equipment obtained through Government excess which will be uneconomical to maintain by FY 1984. The
extremely corrosive atmosphere in the Marshall Islands limits the useful life of vehicles.