CHAPTER Il, SECTION 2
Figure 2-34 shows a temporary 5?-man camp
located on site Nan as of 14 September.
One of the most difficult problems experienced was that of scheduling the use of cunstruction equipment since sutticient equipment was
not available to outfit adequately the construction crews at each camp. This was especially
true of concrete placing equipment, cranes,
trucks and earth moving equipment. The problem was overcome by carefully planning the
equipment usage for each phase of the construction of each structure with the idea of fully utilizing all ecuipment. This involved considerable
movement of the equipment between camps at
each atoll in order to have it avatlable when
required. It also required rigid scheduling of the
various crafts in order that the placement of
reinforcing steel, electrical, mechanical and other
related items would fit the plan for equipment
usage.
Considerable movement of cunstruction personnel between camps wasalso required in order
to utilize fully the restricted manpower available in several of the various crafts. Careful
planning of these movements was necessary to
maintain the construction and equipment usage schedule, but the actual shifting of personnel between camps created no problem.
‘Delivery of materials to construction areas
spread over two atolls required very carctul planning. The main receiving and warehousing facilities were maintained at Elmer on Eniwetok.
and all surface and air freight was shipped to
that point except for some easily identified items
which were off-loaded at Tare, on Bikini. From
this central point at Elmer materials were transshipped to warehouses at Ursula and Fred by
LCMs and LSUs and to Tare by LST. From

Tare, matcrials were again transshipped to ware-

houses at Charlie, Fox and Nan by LCMs or
LSUs. This movement of material from its original puini of receipi to iis final location was always critical due to the tight construction schedule.
The entire construction program was pro-

jected on an Estimated Operations Schedule
which programmed each item of work from design through procurement to the completed
structure ready for occupancy. This schedule
was prepared in the Home Office based on the
known requirments; the Chief Project Engineer
established completion dates for design and
drawings which would give the Procurement
Department the necessary information for scheduling the purchase and delivery of materials
and equipment. With this information the Project Manager and Chief of Operations planned
the actual construction. The schedule was reviewed monthly by all concerned so that corrective measures could be taken as required to

insure completion of the drawings and delivery

of materials as planned.

The major difficulty Construction experi-

enced was the late receipt of approved working

drawings for the Scientific Stations. This in turn
was dueto the late receipt of design criteria. The
dates in February, March and April of 1953
scheduled and set for the development and submission of criteria by the Scientific Using Agencies Were not met.

Construction schedules were essentially met
however, even though an additional test barge
and a major recorder structure were added to
the program in September. The completion
of the work gave the User a chance to schedule

his equipment installations with a minimum of
interference from the constructing forces.

The authorized work week on both atolls
was 54 hours. Any overtime work in excess of 54
hours required prior approval and authorization.
Overtime work in excess of 454 hours was required at intermittent intervals for unloading
ships (off-shore), for marine craft operators,
for handling supplies ashore, for camp operation,
for special services, and, to a verylimited extent,
for actual construction work on the Scientific
Program. The entire overtime pay in excess
of 54 hours averaged less than one percent of
the total payroll. The actual construction overtime was therefore negligible.
The construction progress of Expendable
Construction, based on the Estimated Operations Schedule as noted above, is shown by
Charts 2-1 and 2-2.
It will be noted that
in general the contract items were substantially
completed by their scheduled dates. The summary in Chart 2-2 notes that schedules were
met by February 1954 and then maintained for
the balance of the Operation.
This condition is Likewise reflected in the
progress curve for the over-all program as shown
in Chart 2-3. The estimated schedule in May
i803 was predicated on the receipt of design

criteria and working pans. With the increase
in the scientific work load and having received
the maiorityof the criteria. the estimated schedule was revaluated on 15 November 1953. The
break noted in the curve for April 1954 resulted
from additional work authorized in March 1954
for such items as A-67-C and A-74-C. As Chart
2-3 is based on percentage of completion, the
additional scope of work is reflected in the percentages of estimated and actual completion.
The over-all costs were appreciably less
than was estimated. This is shown in Chart
2-4 where the actual commitments are less
than the estimated commitments. It will be
noted that the actual commitments exceeded
the estimated commitments from 1 June 1953
to 15 November. This was due to the fact that
the estimated commitments were based on the
preliminary planning. As additional tests and
structures were authorized and the scope of
Page 2-57

——eng

Select target paragraph3