CHAPTER Ii, SECTION 1B
sive strengths and unit weights obtained on

was inspected to insure a well-compacted, and

sults of all the limonite concrete test cylinders
show that an average compressive strength of
3259 psi was obtained at ages of 28 days. The inplace unit weights of limonite concrete structures were checked by carefully calculating the
capacity of the forms and comparing the volume
with the number and weights of all batches of
concrete going into a particular pour. Very close
or exact agreements were obtained hetween the
unit weight of the mix design and the calculated
in-place weight. Figure 2-25 shows a foundation
for a Scientific Station. At the right has been

spection after placement, removal of forms and

the limonite concrete pours were good. The re-

-~ywWe
é

aaa[ee

x3

well-bonced and smooth, dense concrete. In-

backfilling was likewise continuous. With the
structure formed, inspection on electrical, sani-

tary, mechanical, piping and similar work fol-

owed,
As to deviations, the very existence and

surveillance of active inspection was a deterrent
to careicss workmanship, particularly since it
was bacxed by top management and respected
by supervision. Its chief function thus became a
reporting agency to the superintendent, who
rectified unsatisfactory conditions directly and
promptly. Authority of the inspectiun service
to correct deviations from plans and specifications was not, however, limited to this level. If
conditions were not rectified, the Resident In-

spector would notify the Chief Inspector who

would refer the matter to the Resident Engineer.
The Resident Engineer would then investigate
and recommend action to be taken by the project Manager. His discretion was used to expedite construction and insure integrity of the
work not only by entorcement of remedial measures, but also by adjusting to material shortages
and functional changes byeffective and controlled substitution.
Safety inspection was assigned as an
additional duty to all Field Inspectors. The
Safety Engineer gave all inspectors a series of
safety lectures defining the required safety stanFigure 2-25.

Limonite Blast Wall for
Station 1342

poured a regular coral concrete pour. The reinforcement shown is for limonite concrete and
this reinforcement must be continuous. In order
to remove the forms for the regular concrete, an
opening was burned out as shown in the center.
With the forms removed, the reinforcing bars
were replaced over the opening and welded ii
place.
FIELD INSPECTION. The Field Inspection
Section inspected all phases of construction work
from the first clearance and grading until final
completion and acceptance. The preliminary
work consisted of studying plans and specifications, bills of materials and any special conditions. Materials were then checked for conformance with specifications and adequacy of amounts on hand and available. The procedure
of work, manpower and equipment to be used
was usually decided in conference with the
work superintendents involved. With the commencement of work, inspection was contin ious.
Excavatiuns and foundations were inspect: 4 for
location, dimensions and orientation; form: were
checked for adequacy; reinforcing rods were
checked for size, bends, spacing, ties and rgidity of support; embedded fixtures were ch cked
for location and size. The placement of concrete
Page 2-50

dards, cperating practices and working condi-

tions. He also issued to them various types of
salety raanuals, especially in regard to safety
Practices in construction, vehicles and job hazards. Jobsite procedure provided that inspectors could hold up work on a project if unsafe
practices were involved, until the unsafe conditions Were rectified.
With work being undertaken at so many
sites and locations, and in order to have uniform
standards, detaiied prucedures were set up in
Tegard to:
1. Approval of construction changes.
2. A weekly construction progress report
noted the percentage of completion of
all outstanding work orders and completion dates for same.
3. Weekly inspection narrative report, a
condensed summary of pertinent mspectyon items noting the difficulties, delays
and other factors affecting the progress
of the work.
4. Inspectors’ ‘‘as-built” corrections, the
procedure to be followed in maintaining
prints in an up-to-date condition and
marking all vanations.
5. Concrete design mix, specifying to Construction the amounts of the various

Select target paragraph3