CHAPTER II, SECTION 7
paper insulated lead armored cable that had
been used in previous installations. Due to the
large amount of cable involved with relatively
short delivery requirement, it became necessary
to spht the order, and approximately 85of
lead armored cable and 15+ of plastic covered
cable was ordered. As of 23 April 1953 when
authorization was received to place the order,
775,000 lineal feet of 16 pair cable was required.
Subsequently the deletion of Scientific Stations
West of site Tare caused a reduction in these

requirements, but the Contractor was authori-

zed by the Manager, Eniwetok Field Othce to accept dehvery of the entire order so that it wouid
be on hand for possible use at other tocations then
unknown, Drawings approved on 30 July i944
indicated that all but 94,000 lineal feet would
be required.

Another departure from previous test
installations was the use of reinforced concrete
vaults for housing submarine cable terminals.
This cable system was designed for use with
several successive tests. These vaults provided
for protection against blast effects and a means
for ready access to the terminal boxes. They
had the further advantage of providing some
protection from radioactive contamination for
the employees required to work at the terminals
between tests. These terminal structures proved
entirely adequate as evidenced by the lack of
damage atter the various detonations and the
few dithcultics encountered in preparing the submarine cable system for each succeeding test.
These terminal vaults consisted of reinforced conercte buildings with a gravel floar and a
3’ x 3’ hatch opening. Stations ST 1.1 through
1.3 and ST 2.1 were 8’ x 8 x 7’ high and projected 1°-0° above grade.
Stations ST 3.1
through 3.4 were 11’ x 11° x &high and projeccted 2°- 6" above grade. Earth fill was placed on
a slope to the tops of the Stations. The location
of Station ST 3.3 was on solid coral and the
building was constructed on grade. Due to the
anticipated high blast pressures, this necessitated the addition of buttresses to this Station
which were embedded one-foot into the coral
with the reinforcing stcel of the buttresses embedded in holes drilled in the coral. This Station
is shown in Figure 2-225. Each of these buildings was equipped with a watertight termina)
box for the submarine cable ends and another

watertight terminal for the termination of lead
covered cables which were run underground to

other Stations.
Figure 2-226 shows a typical
terminal Station with the foundation poured
and the sides formed.
The system as finally installed consisted

of 620,000 feet of 16 pair, 19 gauge sul:marine

cable, running in a single systera from site Able
to Charhe, thence as a double system around
the atoll to Oboe. From Oboe the circuits were
completed to Tare via a 51 pair, 19 gauge un-

Figure 2-226.

S.T. Station - 50% Completed
Typical

derground cable. The reason for the use of 51
pair underground cable for this run was that
the same cable could be used to provide the
signal, control and telephone necds of all the
islands between Tare and Oboe. This was a
more economical installation than providing
submarine cable from the control at Nan to
Tare and separate cables for all other island
needs. Three telephone buuys in the lagoon were
connected to the Tare telephone exchange.
The

signal,

control

and

telephone

cable

system as finally completed is indicated in the
Block diagram Figure 2-227.
The actual mechanics of laving of the cables
were facilitated by fitting out an LCM as a
eahle

lacing
ahh ang

and
Amn

:
eoncis
ropa

banne

TR.

ale
Anwl

awd

bottom of this boat were reinforced, a gasoline
engine driven winch was installed alongside the

wheelhouse and four davits, each carrving a large

sheave, were placed along one side of the boat.
The cable reel was placed in a special cable dolly
in the well deck of the boat, and the cable then
run over the winch drum from where it was
paid out as the boat moved forward. The cable
was laid on a designated course so as to pass

over the shortest distance in shallow water between the terminals. For the long run between
Nan and Oboe requiring 65,874 feet of cable to

be laid in fairly deep water, a helicopter was

utilized for assistance in maintaining the proper
course. Figure 2-229 shows men laying cable in
shallow waters from a terminal station.
The changes effected in laving interisland
cables for the CASTLE OPERATION are
summarized as follows: (1) Cables were gener-

Page 2-228

ee

ent thse tae BA cn DI

eat ‘pagal
aT
hate3
we?

aed wnt lt

oj

Select target paragraph3