CHAPTER It, SECTION 5
snown, was six feet wide by six feet eight inches

CONSTRUCTION. Work commenced or 17
June 1953 and all work was completed on 5

BUILDING NO. 419 - BARGE SLIP
SITE ELMER

as 90°. completed as of 15 October. Figure 2-76

igh.

GENERAL.This stricture consisted of a steel
sheet-pile enclosed mole. 31’ - 3” wide by 86’ - 8”
long, beyond which were two creosoted pile finger piers, each 20’-0" x 132’-0, enclosing a
slip for barge mooring. Spanning the slip was
a stvel gantry crane of 60" - 0” span. The enclosed barge slip was 40'-0” x 130°-0” and was
fitted with guide pile-wings for aid in docking
floating craft. The finger piers were designed to
accommodate a ten-ton tractor crane for loading
or unjoading barges. The pier and slip were used
as an adjunct of the Assembly Area which was
located immediately adjacent to the land end of
the pier. The mole and piers were also available
for the handling of any general cargo. Floodlighting was provided for night operation, and
power outlets were provided as directed by the
User.

MECHANICAL. A steel gantry crane serves
the barge slip. The main hook has a capacity

of 24-tons with a 3%7-font hook lift above the
crane rails. An auxiliary hook with a five-ton
capacity also serves the slip.

ENGINEERING. Theoriginal criteria were received on 6 March 1953. The criteria developed
as the design progressed and many changes were
made. Final criteria were approved on 15 June.
Design work started on 145 April. Four drawings
and one sketch were prepared and submitted
from 29 April to 11 August. Approvals were
dated from 22 Mayto 21 August.

Figure 2-201.

March 1954. Figure 2-200 shows the barge slip

(see Station 10) shows the slip completed with
gantry crane in operation. Barge Stations 10
and 40 were undergoing repairs and alterations
to fit them as Stations.

SCIENTIFIC POWER PLANTS
SITES VARIOUS
GENERAL. The scientific power requirements
known in early 1953 were examined and it was
determined that one central clectric power
generation plant for a closely related group of
Scientific Stations, to be used for one test, would
be the most feasible. A single plant with a few
large units(in lieu of single independent plants)
was more economical to build and operate,

more reliable in voltage and frequency con-

trol, more stable under varying load conditions within the limits of an cconomical distribution system, and where the function of a unitized system could be related to a single test. On
1 May 1953 it was recommended that central
Power Plants for power generation be established at sites Charlie, Dog, Nan, Tare and Ursula.
Oa 5 June 1953 these recommendations were
approved. At site Ursula, IVY Station U-108
was reactivated for this purpose.
At sites
Charlie, Dog and Tare, expendable construction
was used. At site Nan, Building NA-500 was
a 38°-0" x 49°-0" x 14’-0° high reinforced
concrete structure with earth fill on one end
and two sides to the finished grade. ‘The roof
had a two-foot thick earth fill over it and the
exposed end wall of the building had a 15’ - 0”
long by 1i9’-6” high maximum retaining wall

Scientific Power Plants - Typical Feundations

Page 2-202

AO

.
ee

i
:

'

i
\

‘
:

:

awedee eee Gg ssh
‘

.

Select target paragraph3