CHAPTER Ii, SECTION 4

ditional stabilized areas, floodlight plane parking area, P. O. L. office, additional 24 8-man
tents, sealcoating decontamination pad, inspection and repair of three motor generator sets.
and miscellaneous items. Figure 2-53 shows the
new improvements completed on the Fred Airstrip (Contract Item A-40.1), including parking
areas, taxi strips and additional pavement and
marking. Figure 2-52 notes the Decontamination
Pad (Coniract Item A-40.8 and 40.18) at the
northwest parking area en the Fred Airstrip.
Figure 2-54 shows the southwest areas of the

POL Pump House
ENGINEERING. The necessary drawings and
field sketches were prepared by Field Enginering. Tent, trailer and utility locations were
shown on plot plans or on electrical distribution drawings.
CONSTRUCTION. Work wasstarted on ! July
1953 and continued to completion on 31 December 1953.

CONTRACT ITEM NUMBERS A-57-C
THRUA-57.16 — NAN CAMP

Fred Airstrip.

GENERAL. A temporary beachhead camp ca-

ENGINEEPING. The necessary drawings and
field sketches were prepared by Field Engineer-

Nan. This camp was expanded to a construction camp of 100-man capacity. In January
1954 a peak population of 196 men was reached
due to unforeseen Scientific Group occupancy.
This camp was overcrowded and the facilities
were inadequate for two weeks during this peak
load.

ing.

CONSTRUCTION. This construction was continuous during tne Uperaiion and was done as
work was authorized. Figure 2-55 notes the fresh
water tank for the Decontamination Pad (Contract [tem A-40.10). Figures 2-56 and 2-57 show
the P.O. L. Farm on Fred (Contract Item A40.3) completed as of 10 February 1954. Figure
‘2-58 shows Building 94, the P. O. L. Pump
House. Figure 1-3 notes the temporary and
permanent facilities that were required and
added for the Operation. Existing facilities are
likewise shown.

CONTRACT ITEM NUMBER A-44
INCIDENTAL SUPPORT FACILITIES
BOTH ATOLLS
GENERAL. This item consi:ted of a group of
approximately 49 items covering central power

piants for scientific uses only on sites Charlie

and Tare, and other construction for scientific
support essentially, tents, trailer spaces and
utilities.

pable of supporting 40 men was built at site

ENGINEERING. The necessary drawings and
field sketches were prepared by Field Engineering. Figure 2-59 depicts the camp as of 5 Feb-

ruary 1954. The camp had expanded into an

operating camp capable of accommodating 200

men.

CONSTRUCTION. The beachhead was started
on 30 June 1953. The main camp construction
started on 1 September and was completed on
1 December 1953. Figure 1-8 notes the camp
arrangements upon completion of work.

CONTRACT ITEM NUMBERS A-63-C
THRU A-63.9 — FOX CAMP |,
GENERAL. This camp was started on 1 May
1953 with a small beachhead camp. located at

the eastern end of Fox. A new location was es-

tablished for the main 200-man camp and construction began on 18 June 1953. This camp was

i! |

i ‘| Page 2-79
i

' Dae

te eee

As Pies abe ose

Figure 2-58.

Select target paragraph3