William Cooper - Asset. Mgr. Pa

whe

September 5, 1969

10.

Funds for planning, engineering and technical staff support and
labor for cleanup end camp operations were received by the Honolulu
Area Office of AEC from JTF-8 under CRO 69-16, $530,000 and CRO
470108, $500,000 for total of $1,030,000. Costs and commitments
as of August 31, 1969 totaled $712,400.

11.

The estimated average veekly costs from August 31 through the completion of the project (approximately four weeks) fs $25,000. The
estimated weekly cost figure includes labor costs to construct s
water system, stabilize rummy, and other small projects that were

authorized on August 20-21.

The estimated cost of materials for

thege projects, over the estimated weekly coat is $37,600.
Funds available

$

1,030.0 K

Costs and Commitments to 8/31
Uncommitted ag of 8/31

712.4
317.6

Estimated costs for 4 weeks

100 ,0

“Sis

Sub-total

Material for additional projects

37.6

Sub-total

180.0

Estimated cost to rehabilitate equipment
returned to JA.

Estimated Balance
12.

75.0

& DT.

(underrun)

$

105.0 K

The cleanup project was basically completed during the first week
of September vith only punch list items reamining. Work on the
additional projects was started as materials arrived on the project
and as men end equipment were available from the cleanup work. This
work is being expedited to complete by end of September.

It is

anticipated that eny work after the rollup vessel departs Bikini
Atoli can be completed with equipment being transferred to the
. Srast Territory or which is capable of being air lifted back to
Johagton Atoll or to Honolulu.
13.

The H&M force on Bikini on September 3 totaled 29 men.
hae arrived to remove the equipment.

If the ship is late, a small

force of about 10 men will remain to load equipment.
ORIGINAL SIGNED BY
WILLIAM A. BONNET

oFi@ONI303
bec};
SURNAME >

Holmes & Narver, Hono

DATE |....-.----...._---------.02.[.-_--- eee eee een eee
Form AEC-318 (Rey. 9-53)

On Sept. 10

it is planned to reduce this total by about six people. It is
placnad te remove the total work force by September 30 if the ship