JOHNSTON ATOLL

SCIENTIFIC

F&S NO.

TITLE

01015

Payload Checkout Building

USER

STRUCTURE FACILITY NO.

SANDIA

724

FUNDING
AGENCY

AEC

SCIENTIFIC STATION NO.

($000)

BoD

None
ENGR

PROC

FOoD GO+120

CONST

TOTAL

FURN

194. 3

216.8

1.5

42.9

42.9

4,9

259.7

6.4

PRE-GO

Prior Cost

22.5

POST-GO
Estimate 2/67
TOTAL

22.5

237.2

PRIOR YEARS
ENGINEERING
Drawings:

Completed.

91-724-Cl

91-724-W]
JS 91-724-C106

PROCUREMENT

91-724-Al thru A4

91-724-M) thru M4

91-724-S1 thru $4

91-724-E] thru E5

JS 91-724-S100

Completed.

CONSTRUCTION The building is a steel rigid frame structure with aluminum
siding and concrete floor. It is insulated and vapor proof, and is air conditioned
to 76°F. Controls maintain relative humidity to 50 percent. The overall building
area is 50 x 56-ft. with a 23 x 50-ft. central high-bay and a 16 x 50-ft. lean-to on
each side. One lean-to is used for storage and the other for office and laboratory
work. Thehigh-bay area has two motor operated 12x 12-ft. roll up doors and
two bridge cranes. One bridge crane is equipped with a 4-ton, 2 speed electric
hoist and the other with a 2-ton hoist. The storage lean-to has a double 8 x 8-ft.
metal door located at the front of the building. A ]-ton monorail and hoist and
latrine facilities are provided in the office and laboratory area. Power to the
building is supplied from a 408 volt, 3 phase, 3 wire main panel situated in the
high-bay area. The storage area has a 30-ft. candle lighting level. All other
areas are lighted at 80-ft. candle level.
An emergency exhaust system provides an air change every two to three minutes.
Controls are provided to activate the exhaust system, open overhead doors and
shut down the air conditioning system. The building is protected on three sides
by 12-ft. high berms (F&S No.

02065).

A stabilized roadway provides access to

the storage area and a concrete walk connects Buildings 723 and 724.
building and interior appurtenances are grounded.

VOL I

1-16

The entire