Deletion of the requirements for east firing rockets has eliminated the need
for duplicate facilities on each of the peninsulas. Current plans call for use
of Bunker 276 as the Subtask A942 launch control bunker with the in-flight
control vans to be located on the east peninsula. Because of the deletion of
the Subtask A942 requirement for Bunker 737, it is presently planned to utilize this bunker as the Subtask A941 launch control bunker.

POST-GO
PROCUREMENT Two portable 15 H.P. electric driven compressors and
three (3) 70-ft. long wood poles with pole steps will be procured and shipped
to Johnston Island Post-GO.
CONSTRUCTION A 15 H.P. compressor will be installed in each converter
shelter. Three 70-ft. wood range masts will be erected only on the east peninsula. Four TC furnished electric driven generator converters will be installed Post-GO to provide 400 cycle power. These converters will be transferred
to and from each shelter as required.

* Additional construction costs are included under F&S Number 01004.