including five Resident Inspectors, five Assistant Resident Inspectors,
two Batch Plant Inspectors, one Electrical, and one Mechanical Inspector.
The assignment of Resident Inspectors to the principal construction
sites were not permanent inasmuch as maximum utilization of the skills
and experience of the inspectors employed made it desirable to have
them assigned at locations where work in their fields of specialty was
at a maximum,
The duties of the engineering personnel at the site, and of the
inspection personnel in particular, included the interpretation of plans
and specifications, It was, further, the duty of the inspector to determine that work being performed by construction forces was in aceordance with plans and specifications and that all inserts, conduits,
equipment, and the like were properly installed. Checks of scaffolding,
ladders, excavation shoring, and other construction activities were
made to assure that unsafe working conditions were not tolerated, One
of the major items of inspection involved supervision of concrete work,
Each Resident Inspector was supplied with cylinder molds, a slump
cone, and all necessary equipment for taking samples of concrete and
making field tests in accordance with ASTM specifications. When forms
were ready for the placement of concrete, an "Authorization for Concrete
Pour" slip was issued by the Resident Inspector at the locality involved, The Foreman or Superintendent in charge of each phase of the
construction involved was required to certify to the completion of the
phase of work assigned to his group, eg., the completion of forms,
placement of reinforcing steel, inserts, etc, Upon certification, inspection of the work was conducted by the Resident Inspector and if
the work was found in accordance with plans and specifications, the
"Authorization to Pour" was countersigned by the Resident Inspector.
The type and strength of concrete to be used in the pour was
entered on the slip by the Resident Inspector and this served as an
order to the Batch Plant Inspector to supply the Batch Plant Operator
with mix criteria to meet the strength specified, Upon completion of
the routine described, one copy of each slip was distributed to the
AEC Resident Engineer, the H & N Construction Manager, the Statistical
Section of the Engineering Department, and the Test Inspection files.
In December 1949, as part of the Jobsite inspection function, a
materials testing laboratory was temporarily established in a rehabilitated quonset building on Parry. Initial equipment consisted of
scales, a soil analysis screen kit, and two manually operated compression machines, In April 1950, the equipment was moved to Engebi to a
quonset dugout where concrete and material testing was carried out under
the direction of a Chief Technician. This move was deemed advisable
because Engebi was the center of the major critical specification construction activity. In June 1950, a power-driven compression machine
was installed and tested in the Parry laboratory, making possible the
running of accurate compression and tensile tests,

5-30

Select target paragraph3