at any time during the progress of the work the Contract-

ing Officer determines that any subcontractor is incompetent or undesirable, he will notify the Contractor
accordingly and immediate steps will be taken for cancellation of such subcontract.
Subletting by subcontractors shall be subject to the same regulations.
Nothing
contained in this contract shall create any contractual
relationship between any subcontractor and the Government.
GC-V

COMPLETION OF WORK

V-1 POSSESSION PRIOR TO COMPLETION - The Government
shall have the right to take possession of or use any
completed or partially completed part of the work.
Such
possession or use shall not be deemed an acceptance of
any work not completed in accordance with the contract.
If such prior possession or use by the Government delays

the progress of the work or causes additional expense to

the Contractor, an equitable adjustment in the payments
to be made to the Contractor and/or the time of completion
will be made and the contract shall be modified in writing
accordingly.
V-2 CLEANING UP - The Contractor shall at all times
keep the construction area, including storage areas used
by him, free from accumulations of waste material, slash
or rubbish and prior to completion of work, remove any
rubbish from and about the premises and all tools,
scaffolding, equipment, and materials not the property

of the Government.

Upon completion of the construction,

the Contractor shall leave the work and premises in a
condition satisfactory to the Contracting Officer.
V-3

FINAL EXAMINATION AND ACCEPTANCE - As soon as

practicable after the completion of thé éntire work or

any divisible part thereof as may be designated in the
specifications, a thorough examination thereof will be
made by the Contracting Officer at the site of the work.
If such work is found to comply fully with the requirements of the contract, it will be accepted and final

payment therefor will be made in accordance with Article

VI of the contract.

GC-12