Runit (Yvonne) Cleanup and Crater Containment

427

on schedule on [5 November 1977, and crater containment facilities were
ready to begin operation on 15 May 1978.42
CRATER CONTAINMENT PROCEDURES
Concepts for the POD crater containment design and procedures in
CONPLAN I-76 for its execution were developed concurrently. According
to the plans, a mole was to be constructed during the site preparation |
phase (15 June 1977-15 April 1978) to minimize the effects of tides and
storms and reduce the quantity of radiological particles which could escape

to the ocean during containment operations. Later in this phase, when

cleanup Operations began, contaminated soil and debris from the other
islands would be stockpiled on Runit.43 Originally, all contaminated
debris, including that from Runit, was to be collected before the tremie
placement operations were complete in order to insure that it was properly

encased in slurry.44 The POD design and the Field Command Operations

Plan 600-77 (OPLAN) subsequently were amended to allow encasing
contaminated debris during the soil-cement phase by forming a dike
uround the debris and pumping contaminated slurry mix within the diked
area.45-46 When sufficient soil was stockpiled to assure effective tremie

placement of the slurry, containment operations would begin.47.48

Effective placement requires a stockpile large enough to permit as near a
continuous flow of slurry as possible to provide as monolithic a mass as

possible. Stockpiled material would be screened to the maximum size

permitted by the concrete pump. Oversize material would be handled in
the same manner as contaminated debris; i.e., encased in the slurry.?9
During tremie operations, construction would start on the northeast half

of the keywall. By the time tremie operations were complete, most of the
remaining contaminated soil should have been stockpiled so that the

required volume and shape of the dome could be determined.59 The

remaining keywall could then be constructed concurrent with soil-cement
operations. The sequence and timing of these actions werecritical. They
were plannedso as to permit the mosttimely and effective completion of
the project. However, they had to be modified to compensate for
unexpected events.

MOLE CONSTRUCTION
The POD design called for construction of a mole; i.e., a massive wall of

large stones or dike (see Figure 8-9), around the ocean side of Cactus

Crater prior to beginning containment operations in order to minimize the

Select target paragraph3