333

Soil Cleanup Operations

The radiological factors had a major bearing on bulk hauling and werea
factor in the 30-day test period. The possibility of an airborne
dom inant
logical hazard during bulk-haul operation and the ability to
radio taminate bulk-haul boats both needed to be assessed by the experts.

decquestions were extensively researched and evaluated during the test

from HQ JTG, by the FRST,and by the Radiation Safety
personnel
ae
OYit and
Inspection
Team

RSAIT were as follows:?

(RSAIT) from HQ DNA. Thefindings of the
.
_

a. Ait samples consistently indicated that any airborne radioactivity

level was less than one-tenth of the maximum permissible
concentration (MPC). This levelof activity did not require respiratory

protection.
b. Crews did not experience difficulty in decontaminating the load area
of the craft, although the process did require additional hours to

certify decontamination.

The bulk-haul evaluation demonstrated conclusively the efficiency and

radiological safety of the system. After receiving a detailed written and
verbal report from the RSAIT, the Director, DNA approvedthe use ofthe
bulk-haul procedure for soil transport. It continued to be improved during
subsequent soil removal operations. It was one of the more important
innovative techniques developed during the project,? and withoutit the

cleanup would have required more time and/or resources.

AOMON (SALLY) ISLAND SOIL CLEANUP
The Department of Energy-Enewetak Radiological Support Project

(DOE-ERSP) fine soil survey of Aomon began on 23 February 1978 in

preparation for the pilot soil removal project. Three areas had been found
to have transuranic contamination above acceptable levels. These areas,
shown in Figure 7-6, were around the Kickapoo and Yumatest ground

zeroes (GZ) and in a third location which the JTG designated the
‘‘|fustead’’ area after the then U.S. Army Element (USAE) Operations

Officer (S-3). Pilot soil removal work began in the Kickapoo area on 8

March 1978, The pilot soil removal project evolved into a full-scale cleanup
of contaminated soil on theisland.Soil profile and in situ surveys following

each 6-inch lift indicated swirls of contaminated and noncontaminatedsoil

muchlike the swirls of color in a marble cake. This ‘‘marble cake’’ effect
resulted from earth-moving actions between and following nucleartests.
Severallifts were required to meet theinitial target level of 80 pCi/g.

After the three areas were IMPed in June 1978, it became evident that
removal of a limited amount of additional soil would allow the island to
meet residential levels (40 pCi/g). There was a narrow strip in the

a

Select target paragraph3