departed RONGELAP Atoll.The construction job per se was a simple one.
However, it required
a great deal of planning and cooperation by the many governmental agencies
involved.
The construction effort is presented both pictorially and graphi-
cally at the end of this Narrative Summary.
Part II of this report pre
sents the Pictorial Review and Part II] Building Lists and Plot Plans of the
reconstructed villages.
For record purposes a building list and plot plan
of RONGELAP, as determined by a Holmes & Narver survey party on 27
April, are also included. (1954)
On 20 June 1957 representatives of the AEC and Holmes & Narver
met with the District Administrator at MAJURO for a discussion of acceptance of the construction.
The District Administrator stated that he
had conferred with his representatives at RONGELAP and was prepared
to accept the RONGELAP program with the exception of that scheduled for
AILINGINAE.
In the interests of economy the scheduled transfer of cis:
terns and building materials to AILINGINAE had been deferred.
The ac-
ceptance by the Trust Territory Government would be confirmed byletter
from the High Commissioner.
The off-loading of the cisterns and the
miscellaneous construction materials at AILINGINAE was accomplished
ll July 1957.
Therefore, this is the completion date for work performed
by Holmes & Narver in accordance with plans and specifications approved