CHAPTERII
SECTION 2
Bldgs. 43, 44, 51 - 55 inclusive, 115, 122, 123, 125, 127, 130

Latrine and Showers
1.

Locked all shutters and doors in open position

2. Roof in shower room was supported
3. Additional securing studs were driven in sill plate angles
Bldg. 56 - Power and Distillation Plant:
1, All doors were rernoved
2.

Alternate shutters were removed and all others were locked

in open position

3. Wall panel below shutters was removed intact
4. End walls were braced
5.

Cable stays and roof support were provided

6. Posts under frames with columns omitted
7. Additional securing studs were driven in sill plate angles
Bldg. 77 - Drone Headquarters:
1, All doors were removed

2. All shutters were locked in open position
3. All bookcases and files were laid flat
Bldg. 85 - Receiver;
1. All shutters were locked and doors were closed
2. Building frames were braced
3. End wall facing blast was braced
Bldg. 89 - Base Operations - and Control Tower:
1,

6-42

All doors were removed

VOL, Il
BOOK 6