VOL.
BOOK 5

IV
CHAPTER
SECTIONS 12 - 14
SECTION 12.

TASK UNIT 11

Support rendered Task Unit 1! by Holmes & Narver consisted solely of
the installation of a drinking fountain with fresh water supply at Station 1 on
Site Flora, Four man hours were involved.
SECTION 13.

PROGRAM 1

PROJECT 1.3. The placing of a steel box atop Station 300 at Site Alice, as
directed by LASL-J-11, was the extent of services provided to this Program.
Total man hours were 18.

SECTION 14.

PROGRAM 2

PROJECT 2.la. Miscellaneous services supplied to this program included
installation of cables required to deliver three timing signals to NRL's location

in Bldg. 232 on Elmer, and installation of a seven-quad cable furnished by

NRL, between the Site Elmer telephone switchboard and Bldg. 232. In addition, a "30° Hot Mounting Plate" was fabricated according to NRL specifica-

tions; men and equipment for handling the User's material were furnished; a
motor was rewound and a room cooler compressor checked; power was provided and connections made to two NRLK trailers in the Site Elmer AEC Compound (a three-phase four-wire circuit of 60 amps and 208 volts was required

for each trailer); a forklift and operator were furnished to NRLK to load pallets
of lead bricks into trailers at Site Elmer, for three working days; a fresh-water

line was furnished to an NRLK trailer at Site Elmer; material and equipment

were provided for the purpose of cocooning the doors of five NRLKtrailers.

Other Holmes & Narver services were provided to Program 2 Users at
specified stations,

listed below:

STATION 1 - SITE FLORA. A shelter was constructed over the compressor
for an NRLK dehumidifying unit.

STATION 200 - SITE ALICE. Three blowers were installed to ventilate Station
200 pending the arrival of scheduled dehumidification units (this step was re-

quired to expedite installation of copper shielding); an extension to the sump

pump discharge line was installed to carry discharged material into the ocean;
a decrease to one-third of the existing rate of air delivered to the coax room
was effected at the User's request; six electricians were furnished to make a
rapid cut-in of electromagnetic filters; two laborers were furnished to load
equipment into an NRLK trailer on M -3 Day and M -4 Day; and one electrician

and one refrigeration man were requested to stand-by until 2400 hours on M -1
Day.

5-12

Select target paragraph3