9, Process and store the remaining camp equipment including beds, mattresses, pillows, lockers, etc., an estimated 40 percent. 10, Complete repairs to and secure beached marine craft; this item is estimated at 60 percent complete, The processing of marine craft required to be placed in floating storage is awaiting the arrival of a dry dock. ll. Charge and store approximately 1,000 storage batteries. This item is awaiting a decision by AEC as to whether storage or replacement of these batteries will be more economical, 12, Repair personnel dock, 13, Close and secure the Rad-Safe Building, 14. Overhaul power plant equipment. 15. Move steel storage under cover and treat all plates and shapes with rust preventive. 16. Repair the concrete marine ramp. ENIWETOK 1. Overhaul power plant equipment. 18-8