Progress - %
Schedule
Cappletion
Scheduled Actual

item

Remarks

ElectricalDept.

Clean, Repair, and Store

Portable Generators

25%

40%

September 1

*

* Scheduled completion date not firm, but dependent upon manpower

The following list consists of items of work to be campleted on

each island as of the end of June 1951 and is intended to indicate the

nature of the work remaining without attempting to define the exact
scope of the unfinished operations.

ENGEBI
1. Contime to secure scientific structures and paint blast doors.

2. Pickup and ship to Parry collimator boxes for "E+”
3. Repair No. 20 blast walls sufficiently to obliterate the blast
effects and paint exposed steel work.

4. Fill holes in the dock.
5. Contime overhaul of power generator units.

6. Continue work on water distillation units.
7. Make crater survey.

MUZIN
1. Complete diamantling of the remaining half of the 3.3.3 Hangar
Building and ship salvaged steel to Parry.

GROUP
1. Pickup and ship the remaining collimator boxes to Parry.
2. Contime to secure the scientific stations and paint blast doors.

3. Prepare blast walls as for Engebi.
4. Continue overhaul of power generation units.
5. Contimie work on water distillation units.

6. Make crater survey.
18-6