CHAPTER 14.2
MATERIAL TRANSPORTATION
The transportation of materials was a major logistic problem be-

cause of the isolated location of the Jobsite, the magnitude of the

Project, the changes in scope of the work, and the unanticipated diversion
of transportation facilities to meet requirements of the war in Korea.

SURFACE SHIPMENT
Because of the high tonnages involved, the basic transportation

channel for material was, of necessity, surface shipping. At the beginning of the Project, estimates were made of cargo requirements, but,

because of the greatly increased scope of the work, these were greatly
exceeded. Table 14.2-1 shows a comparison of estimated and actual
cargo tonnages by months.

It will be noted that after March 1950, the estimated cargo require ments were 300 measurement tons per month, which included dry provisions and
and chiiled and frozen provisions. This was considered to be a maintenance figure which would obtain for the remainder of the Project, as

it was expected that all basic construction equipment and material
would be at the site by that date. It will also be noted that as of

Marck 1950, the actual and estimated cumulative cargo were in agreement
within 7 measurement tons. From that date forward, the actual tonnage
soared upward radically because of the addition of the Military Struc-

tures Program, the Scientific Structures Program, and a general increase in the scope of the Project. For the twenty-four months from
June 1949 to May 1951 inclusive, the total tonnage actually shipped
averaged 2810 measurement tons per month.
Throughout the Project, because of limitations on warehousing
space and the shortage of personnel to devote to stevedoring, it was

necessary that cargo be so scheduled that it would arrive at the Project
at intervals ofnot exceeding thirty days.

It was accordingly arranged

with Naval personnel at the conferences at CincPac in June 1949 that
ons general eargo ship and one refrigerator ship would sail from Oakland
at intervals of approximately thirty days, each carrying H & N cargo.
It was anticipated that the space allocated to H & N would be adequate
for requirements. It was necessary that items of equipment and construction material arrive at Oakland on a schedule as designated to

accommodate the construction schedule. After negotiation with Naval
authorities, the Western Sea Frontier was designated as the liaison
channel for Navy logistic support on the West Coast. Working arrange-

ments were made with the warehousing and ship loading agencies of the
Navy at Oakland, and later with MSTS when it was established.

In actual practice, certain difficulties developed in the shipping

arrangements.

These were unanticipated and caused serious dislocations

in the orderly progress of construction.

14-6

Most of these difficulties

Select target paragraph3