of funds. The Engineering Department had completed the designs for interior power and lighting requirements, and bids had been advertised and

received on the basis of the complete bill of materials, but no award

could be made for these items until later. A check survey of transformer requirements against Los Alamos and Oak Ridge excesa listings was
in process. Power generating units were designed and competitive bids
had been received, but the award was withheld. The first orders for
water distillation units to augment the capacity of the rehabilitated
water stills located on-site, were awarded in May for estimated delivery
in July. All non-critical replacement motors, clutches, and compressors
required for maintenance of the existing water stills had been shipped
complete on June 23. All critical small repair parts for the stills had
been previously forwarded via air.
Personnel transport vehicles were secured for Jobsite use during
the second quarter. An order for fourteen new dump trucks had been
placed by the Atomic Energy Commission for delivery July 27 to the Naval
Supply Center. The camp maintenance planning was underway and the Engineering layout for laundry facilities had been approved and advertising for bids for equipment and materials was accomplished.

The third quarter of 1949 was a period of continued expansion in
the Procurement organization. (See graph, Figure 13.2-4.) Likewise

during this quarter, procurement operations continued at an accelerated
pace. All primary plumbing and piping facilities had been secured, with
considerable quantities being furnished from surplus supplies at the los
Alamos and Hanford Atomic Energy Commission bases and charged to Contract
AT~(29-1)-507. Supplemental quantities of electrical materials were

ordered, and the first fuel handling equipment orders had been scheduled

for shipment September 1. Arrangements had been made to obtain monthly
allocations of fuel from the U. S. Navy, and storage facilities were being

prepared.

The initial orders for diesel-electric power generating plants had
been placed for fourth quarter delivery, and repair parts had been furnished to maintain temporary output of the 75-kw generating plants located
at the Jobsite. Several additional 75-kw plants were obtained from Pearl
Harbor to augment these temporary power facilities. A similar situation
existed regarding refrigeration facilities, and miscellaneous equipment

had been purchased and shipped to maintain the eleven 650 cubic foot capacity portable units that were the property of the government on-site at

Eniwetok,

Requisitions had been placed with U. 3S. Navy at Port Hueneme

for walk-in type refrigeration boxes, and these units were scheduled for
shipment in early September,

Two steam boilers for campsite facilities

had also been purchased for September shipment, as well as the necessary

replacement parts for the smaller type temporary boilers already located
at the Jobsite.

Materials and pile-driving equipment for the first test pier had
been shipped by August. All laundry equipment, mess hall and bakery
equipment, and their respective supply requirements had been purchased
for September shipment, Additional temporary housing consisting of sixteen tents had been provided, and orders for the initial stock of dormitory furnishings and lockers had been placed.

13-12

Select target paragraph3