176

RADIOLOGICAL CLEANUP OF ENEWELAK ALOLL

Operation Switch also created increased demands for billeting at

semiannual sampling and reporting of radiation in fish and wildlife, and
Field Command objected to this condition on numerous grounds.??

Enewetak Atoll. Building 686 on Enewetak was pressed into service as
overflow billets, and incoming personnel who were scheduled to work in
the north were sent promptly to Lojwa Camp. There were some problems
in retaining necessary skills to assure continuous operational capability
during the exchange—and, as was obvious, the loss of experience,
continuity, and working relationships was staggering. In general, however,

In formulating the crater containment permit, a standard provision was
included by the Corps of Engineers which would have required DNA to
maintain the structure in good condition indefinitely. (The general
rationale for this position was: Cactus Crater presently exists on the
northern end of Runit Island; Cactus Crater extends below the water
table, thus it is filled with water; since Cactus Crater is filled with water,
even though it is located partially on the reef, the probability exists for
migration of its water to and from the lagoon dueto tidal action, thereby

Operation Switch I-was very successfully executed. 104

MOBILIZATION/CLEANUP OVERLAP

making it subject to the laws governing the introduction of materials into
navigable waterways; a plan to fill Cactus Crater with a concrete slurry

Although 15 November 1977 was identified, for scheduling and record
purposes, as the end of the Mobilization Phase and the beginning of the
Cleanup Phase, in practice, mobilization and cleanup efforts overlapped by
several months. Some cleanup operations began long before I5 November
1977, and some mobilization efforts were not completed until much later.
During the first week of December 1977, seven navigational aids were
installed by personnel of the U.S. Coast Guard Enewetak LORAN Station,

mixture equates to building a structure on a navigable waterway; the
standard provision requires that anyone building a structure on a navigable
waterway must commit themselves in writing to perpetual maintenance of

the structure.) DNA objected to this provision as being inappropriate and

pointed out that it was directly contrary to all U.S. commitments, directly

contrary to the national-level decisions made after 3 years of debate, and in

with technical guidance by Mr. Steve Guishikuma of the [4th Coast Guard

violation of Congressional guidance. Agreement was reached eventually

that DNA would maintain the structure until the project was complete,

District, and with boat support by the USNE. Navigational lights were
installed at the Enewetak personnel pier, on the derelict concrete ship off
Japtan, on the Point Oscar survey platform, on the east end of Biken
(Leroy) Island, and on the Janding ramps at Runit, Lojwa, and

and thereafter would assure that periodic monitoring of the site was

accomplished by some Federal agency until the United States terminated
its trusteeship responsibilities. !0°

Enjebi.!05.106 These aids significantly increased the safety of boat
operations at dawn and dusk, and for any emergency boat operations

Resolution of all these issues took an inordinate amountof time, and it
began to appear that either the permits would have to be ignored or the

absence of permits was going to halt work on the project. The channel
clearance permit was finally issued on 31 August 1977, 2 weeks before
blasting began.!9! The lagoon disposal permit was issued on 3 November

1977, 102 The crater containment permit was not issued until 9 November

1977, the week before the Mobilization Phase officially ended and the

977 began in October 1977, and the turnover in November was near-total.
Over 400 personnel were replaced in that month in an exchange termed
Operation Switch. It required extensive planning and close coordination by

the JTG, the Service Eiements, and Field Command’s Pacific Support

Office, which scheduled the airlift and coordinated Operation Switch
actions in Honolulu.

Pe

Mostmilitary personnel were replaced after serving 4-6 months TDY at
Enewetak. Replacement of the personnel who arrived in May and June

oo ee ee -e=--—~7

+

Cleanup Phasebegan. !93

OPERATION SWITCH I: NOVEMBER 1977

fan

Moeouizaiio

required during the hours of darkness.
As was previously noted, Lojwa camp construction was seriously behind
schedule, and CJTG was urging that work be accelerated to provide
beneficial occupancy as scheduled by 15 November 1977. Through many
well-conceived and well-directed actions, this was achieved, although
some facilities were incomplete. The power plant, distillation plant, billets,
and most other major facilities were complete, however, the dining hall
was not used until 25 December 1977, when the first meal served was

Christmas dinner. Burnout latrines and water trailers were used until
planned facilities were finished.!°7 Temporary water lines and other

makeshift facilities were gradually replaced, some aslate as February1978,
as Camp construction phased into camp maintenance (Figure 3-20).
Through superb teamwork as well as many outstanding individual
elforts, mobilization for

:

é

:

success. By 15 November 1977, the base camps were readyto support the
cleanup forces. The equipment to locate, remove, and dispose of
contaminated material was on hand, and the forces were deployed and
ready to begin cleanup operations.

Select target paragraph3