154

RADIOLOGICAL CLEANUP OF ENEWETAK ATOLL
FIRST LOGISTICS CONFERENCE:18-19 APRIL 1977

Field Commandwas responsible for coordinating mobilization efforts by
the Defense Agencies, the Military Services, and other government
agencies and contractors. On 18-19 April 1977, their representatives met at
Headquarters, Military Traffic Management Command, Western Area

FRaree

‘

—
:
ar
eeate ne ee miei
so
Se
~ on
cere
RRR = arenea pO

(MTMCWA) in Oakland, California, to coordinate supply and —

transportation actions. The conference was called and chaired by Field
Command’s chief logistician and was hosted by the Commander,
MTMCWA. Thegoal of the conference was to identify what cargo was
available, when it was needed, and the most effective, economical means

of getting it to Enewetak.

Primary concerns were acquisition and delivery of equipment and
supplies for the U.S. Army Element (USAE) to begin Lojwa Camp site
preparation on 17 May 1977 and Lojwa Camp construction on [5 June 1977.
The Military Sealift Command (MSC) ship American Racer, which was
due to call at Enewetak on 3! May 1977, could deliver most of the material.
Almost 5,000 measurement tons of cargo were identified which would be
available to ship on the American Racer. This ship was one of the deepdraft vessels which MSC used to deliver cargo between ports in the Pacific.
It could not be offloaded directly at the Enewetak cargo pier, where the
water was only 8 feet deep, but would have to be anchored in the lagoon

and offloaded into lighters which could, in turn, be offloaded on the piers

or beaches. The COMNAVSURFPACrepresentative agreed to expedite
deployment of crews for the landing craft which were scheduledto arrive
at Enewetak on 8 May 1977 so that they could be used to offload the
American Racer. Field Command, U.S. Army Forces Command, and
H&N-PTD representatives began developing plans for stevedores to
offload the ship and for shallow-draft barge service for future resupply of

the atoll.39

It was determined that items required prior to the ship’s arrival could be

provided by loan of some base support contractor equipment and byairlift

of other critical items via scheduled MAC flights. Field Command also
agreed to finance a special C-5 airlift to deliver four helicopters and other
critical items from Hickam AFB in time to meet 17 May 1977 materiel
requirements. The confereesalso identified four landing craft, three Army

Mobilization

155

The Logistics Working Group used the 29 April 1977 OPLAN
Resolution Conference to further refine plans for offload of the American
Racer and implementation of shallow-draft barge service to Eneweta
k
Atoll. It was agreed that H&N-PTD would offload Navy-operated landing
craft at the beach, that the Racer’s crew would operate its winches, and
that the Army would provide one officer and 19 enlisted men from Fort

Eustis, Virginia, to offload the ship.49 The conferees also formally

requested the Commander, MSC to provide shallow-draft barge service

between Pear! Harbor, Johnston Atoll, and Enewetak Atoll.4!

TRANSPORTATION UNITS ARRIVE: 3-16 MAY 1977
On 3 May 1977, six enlisted personnel from US. Navy Assault Craft

Unit ONE (ACU-ONE) arrived at Enewetak Atoll to receive and put in

service the first increment of landing craft which were to be delivered on 7
May 1977 by a Navytask group returning to the U.S. from Naha, Okinawa.
The convoy consisted of the USS MONTICELLO, the USS
VANCOUVER, and the USS SAN BERNARDINO. They delivere
d one

landingcraft, utility (LCU), three LCM-8s, one warping tug, three 90-foot
causeway sections, and other equipment?2 totaling 4,493 measurement

tons. The craft were promptly inspected and serviced by the ACU-ONE
team. Sea trials of the LCM-8s were conducted during the next week,
and
they. were put into service for lightering and support of Lojwa Camp.

construction.
Another early arrival was the Air Force airfield team, which landed
on [0

May 1977. It was operational by [5 May 1977 when the next C-5 aircraft
arrived at Enewetak and offloaded four UH-I helicopters and other critical
Army equipment. Maintenance and flight crew members accompanied
the
helicopters to prepare them for use. The Air Force communications
installation team and their equipment redeployed to Yokota, Japan, on the
same aircraft.43 On the same day, the petroleum supply ship, USNS
RINCON, delivered fuel to top off the diesel, gasoline, and aviation fuel

(JP-4) storage tanks.44

LARCstwoexplosives anda variety

ADVANCE PARTY ARRIVES: 17 MAY 1977

1977. The conference not only solved many mobilization problems but
reinforced the momentum and positive working relationships generated in

On 17 May 1977, an advance party consisting of the Commander, JTG
(CJTG), the base camp construction forces, and the support teams
arrived. By the original CONPLAN, their arrival was to be the event
signalling D-Day—the first deployment of camp construction forces.
Under the OPLAN, D-Day was established as 15 June 1977.

of general cargo which wouldbe available for a special Navy sealift in June

developing the OPLAN, and extended them to the supply and
transportation agencies which would be supporting the project from the
West Coast.

Select target paragraph3